PLM315 Maintenance Processing: Operational Functions
Unit 03 Notification

Which of the following is True about Maintenance Notifications ?
(more than one answers)

(A) A Task list must be assigned to a manually created notifications if the correct corresponding tab strip has been activated in customizing for the notification type.

(B) If the notification has a task list assigned, the operations of the task list can be copied to the operation list of the maintenance order.

(C) If a notification is deleted from the object list of a maintenance order, all the corresponding operations that came with the task list of the notification are deleted from the operation list of the order.

(D) If the operations linked to a notification are deleted from the operation list of the order, the corresponding notification is not deleted from the object list.

(E) The notifications assigned to an order are copied to the object list of the order; However, only one notification can be assigned as the header notification.
.