Question no 3299 : Project System Structure Assignments

In SAP PS as at ECC6.0 EhP6, which of the following assignments in PS are correct ?

(more than one answers)

A)  more than one network structure can be assign to one Operative Project.
B)  one of more network activities can be assign to a WBS.
C)  activities from more than one network structure an be assign to a WBS.
D)  a project cannot be saved without a network structure.
E)  one or more project definition can exist in a Project structure.
.

Question no 3298 : Key Profile when creating Project

In SAP PS as at ECC6.0 EhP6, which of the following is the key Profile use to create Template/Standard and Operative Project Definition and WBS ?

(only one answer)

A)  Project Definition.
B)  Settlement Profile.
C)  Default Profile.
D)  Project Profile.
E)  User Parameter Profile.
.

Tuesday, September 14, 2010

Question no : 481 PS Master Data Basics

TERP10 (Unit 10) Program and Project Management 
.
A useful tool in SAP PS which allows you to efficiently edit and access your project is the _______________ . 
   
(Select ONE best answer)

A)   Easy cost planning.
B)   Manager's desktop.
C)   Work Breakdown structure. 
D)   Project builder. 
E)    Engineering workbench.

Sunday, August 29, 2010

Question no : 453 PS Master Data WBS and Activities

TERP10 Quiz Unit 10 Program and Project Management

Which of the following objects can be assigned to a WBS element or Activities ? 

I)       PS texts.
II)      Documents.
III)     Milestones.
IV)     Settlement profile.
.
A)      II, III.
B)      II, III, IV.
C)      I, II, III.
D)      I, II, IV.
E)      I, II, III, IV.
.

Question no : 452 PS Master Data WBS Operative Indicators

TERP10 Quiz Unit 10 Program and Project Management

Which of the following Operative Indicators should be assigned to a WBS element to allow posting of revenues ? 

A)     Planning element
B)     Account Assignment element.
C)     Billing element.
D)     Execution element.
E)      Settlement element.
.

Question no : 451 PS Master Data WBS Operative Indicators

TERP10 Quiz Unit 10 Program and Project Management

Which of the following are valid Operative Indicators for a WBS ?

I)       Planning element
II)      Account Assignment element.
III)     Billing element.
IV)     Execution element.
V)      Settlement element.

A)      I, II.
B)      I, III.
C)      I, II, III.
D)      I, II, III, IV.
E)      I, II, III, IV, V 
.

Tuesday, February 23, 2010

Question no : 299 PS Organization Concept

TERP10 (Unit 10) Project System 

The highest level of definition in a Project structure is the _________________ . 

(Select ONE best answer)

A)   Project definition. 
B)   Company code.
C)   WBS elements
D)   Client.
E)    Network graphics.