Question no 3576 : Serial Number Profile in PM

In SAP PM as at ECC6.0 EhP6, the Serial Number Profile is assigned to which of the following object ?

(only one answer)

A)  Material Master.
B)  Equipment.
C)  Serial Master.
D)  Maintenance Profile.
E)  Planning Plant.
.

Answer: A

Plant/Storage view 2

Wednesday, November 8, 2017

Question no 3463 : Serial and EQ synchronization

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following settings ensure that the Serial and Equipment Number are synchronized ?

(only one answer)

A)  Serial Profile.
B)  Equipment Category.
C)  Serial Category.
D)  Serial Level.
E)  Creation Profile.
.

Answer: D

Material Master Plant/Data Storage view 2

Thursday, September 18, 2014

Question no 2561 : Serial Profile for SAP Plant Maintenance

In SAP PM (ECC6.0 Ehp5), the Serial Profile for Plant Maintenance related Material Master definition allows you to do which of the following EXCEPT ?

(only one answer)

A)    Determine if Serial Number creation is mandatory at Goods Receipt.
B)    Determine if Equipment Number creation is mandatory at Goods Receipt.
C)    Determine if Serial Number creation is mandatory at Purchase Order Creation.
D)    Determine if Serial Number creation is mandatory at Purchase Requisition Creation.
E)    Determine Synchronization of Serial Number and Equipment Number when they are created.
.

Tuesday, September 16, 2014

Question no 2650 : Plant level definition for PM Technical Object configuration

In SAP PM, which of the following technical object configurations are not defined using Plant level ?

(more than one answers)

A)    Structural Indicator.
B)    Functional Location Category.
C)    Equipment Category.
D)    Serial Number Profile.
E)    Reference Functional Location Category.
.

Friday, June 27, 2014

Question no 2407 : Serial folder in the Equipment Master

In SAP Plant Maintenance ECC6.0 EhP5, which of the following information can be found in the Serial data folder in the Equipment Master ?

(more then one answers)

A)    Stock type.
B)    Valuation costs of material serial.
C)    Valuation type.
D)    Purchase Order number.
E)    Storage information at Plant and Storage Location.
.

Thursday, June 26, 2014

Question no 2406 : IE4N (ECC6.0 EhP6) in Plant Maintenance

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following processes are now available in the transaction IE4N (Dismantling/Installation with Goods Movement) ?

(more then one answers)

A)    Non-Serial Material Installation with Goods Movement.
B)    Non-Serial Material Dismantling with Goods Movement.
C)    Serial Material Equipment Installation with Goods Movement.
D)    Serial Material Equipment Dismantling with Goods Movement.
E)    Equipment Swap or Exchange.

Wednesday, June 25, 2014

Question no 2405 : Serial Profile for Equipment Master

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following are configured within the Serial Profile in the customizing which is assigned to the material master for serialization of the material ?

(more then one answers)

A)    It contains the serial level to synchronize material serial number with equipment number.
B)    It contains procedure to control requirement of serial number at purchase order creation.
C)    It contains an equipment category where the equipment master will be created at goods receipt.
D)    It contains an asset class where the asset master will be created at goods receipt.
E)    It contains procedure to control automatic installation of equipment to functional location at goods receipt.
.

Tuesday, August 14, 2012

Question no 1641: Serial Profile

In SAP PM as of ECC6.0, the Serial Profile assign to the material master do not have which of the following parameters ?

(more then one answers)

A)    Control the Synchronization of Equipment and Serial number.
B)    Equipment category type default.
C)    Ensure equipment creation is necessary during goods receipt.
D)    Alignment of Asset, Serial, Equipment during goods receipt.
E)    Set serial number user status for the Serial Master.
.

Monday, August 13, 2012

Question no 1640: Sychronization of Equipment and Serial

In SAP PM as of ECC6.0, the setting in-order to synchronize the equipment and serial number is done where ?

(only one answer)

A)   Material type configuration.
B)   Serial profile configuration.
C)   Serial level in the Plant/Storage view.
D)   Equipment type.
E)   Serial number range.
.

Sunday, March 20, 2011

Question no 1017 : Synchronization of Equipment and Serial

In SAP PM, when the equipment number created is synchronized to the serial number, this means which setting has been done ?

(only one answer)

A)    The equipment category contains the synchronization setting.
B)     The serial profile assigned to the material number contains the synchronization's setting.
C)     During goods receipt, the synchronization setting is selected.
D)     A configuration is done at the Plant Parameter in customizing.
E)     The serial level in the material is set to ensure synchronization.
.

Thursday, March 17, 2011

Question no 1014 : Serial Profile

In SAP PM, which of the following are true about Serial Profile ?

(more then one answers)

A)      It determine synchronization of serial number and equipment number.
B)      It determine synchronization of asset number, serial number, and equipment number.
C)      It determine equipment category to used to create equipment in goods receipt of purchase order.
D)      It determine serial number requirement in selected logistics processes.
E)      It determine construction type material to be equal to serial material.
.

Tuesday, November 30, 2010

Question no : 737 PM Master Data Serial Number Usage

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

The following statements are true about serial number usage for plant maintenance:
(more than one answers)

(A) It is possible to carry out physical stock count.
(B) If several users simultaneously attempt to create serial numbers for the same material number, a lock ensures consistent number assignment
(C) The serial number master record provides stock information for stock type, plant, and storage location.
(D) The combination material/serial number/equipment number can be unique.
(E) It is now possible to use the IE4N transaction for simultaneous Removal/stock return or Installation/goods issue.
.

Question no : 736 PM Master Data IE4N

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

When removing equipment that is serialized with a material number from the functional location using the transaction IE4N :
(more than one answers)

(A) It is placed in the storage location.
(B) It is removed from the storage location.
(C) It requires a movement type.
(D) It generates a notification order.
(E) It generates a material document number.
.

Question no : 735 PM Master Data Serial Number List Editing

PLM305 Structuring and Managing Technical Objects 
Unit 04 Serial Numbers

The “Listing Editing – Create” transaction in serial number allows you to:
(only one answer)

(A) Create serial numbers.
(B) Create report variant.
(C) Create field selection.
(D) Create a report list.
(E) Create a material number. 
.

Question no : 734 PM Master Data IE4N

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

The transaction “Remove/Install with goods movement” where when you use the “install” function will:
(more than one answers)

(A) create an accounting document.
(B) remove stock from the storage location.
(C) create a cost accounting document.
(D) install the equipment in a functional location.
(E) status “ESTO” is now updated to “INST” in the equipment master.
.

Question no : 733 PM Master Data Serial Number Profile

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

The serial number profile provides the following control features:
(more than one answers)

(A) Ensuring the equipment number and its serial number assigned to it is synchronous.
(B) Ensuring the construction type and material number are kept synchronous for a serialized equipment.
(C) Ensuring that the serial number master record must first be created before it is used in the plant maintenance transactions.
(D) Ensuring the system to do a stock check during serial number assignment.
(E) Entry that determines whether or not an equipment master record should be created for each number when assigning serial numbers.
.

Question no : 732 PM Master Data Serial Number Master Data

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

Serial number master records update stock information for:
(more than one answers)

(A) Plant, storage location data.
(B) Unrestricted stock, Stock returns from customer.
(C) Special stock scenario.
(D) All non-stock items with outstanding purchase orders.
(E) All stock types.
.

Question no : 731 PM Master Data Serial Number Profile Configuration

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

The serial number profile configuration controls the following ?
(more than one answers)

(A) Serial number for a master object must be in existence when goods issue is performed.
(B) Serial number for a master object need not be in existence and is generated only when goods issue is performed.
(C) Equipment number is not required during goods issue as it can be generated.
(D) It is possible to perform goods receipt without equipment number but with serial number.
(E) Which equipment category that the system uses when assigning serial numbers automatically in the case of equipment master records.
.

Question no : 730 PM Master Data One-Step Installation

PLM305 Structuring and Managing Technical Objects
Unit 04 Serial Numbers

In a single step, you can remove a piece of equipment from a storage location and install it at another piece of equipment or a functional location, which transaction would you recommend to perform this task ?
(only one answer)

(A) IE02.
(B) IL02.
(C) IH01.
(D) MIGO.
(E) IE4N.
.