Question no 4057 : Control Parameters for Production Orders

In SAP Production Planning & Execution as at S/4 1909, which of the following Parameters provides the following controls:
. BOM and Rouning selection
. Batch Determination Procedure
. Status Change Documentation
. Costing Variants for Planned and Actual Costs

(only one answer)

A)  Order Type Plant independent Parameter
B)  Order Type Plant dependent Parameter
C)  Confirmation Parameter.
D)  Production Scheduler Profile.
E)  Non of the above.
.

Answer: B

Monday, September 14, 2020

Question no 3734 : Available Capacity

In SAP PP as at ECC6.0 EhP6, which of the following is the correct Available Capacity based on the data provided ?

Work Time: 09:00 - 18:00
Break Time: 1 hour
No of Capacity: 4
Capacity Utilization: 80%

(only one answer)

A) 25.6 hours
B) 32 hours
C) 36 hours
D) 28.8 hours
E) 320 hours
.

click "1 comment" for possible solution

Wednesday, September 2, 2020

Question no 3730 : Work Center Capacity

In SAP PP as at ECC6.0 EhP6, which of the following are correct for Work Center Capacity ?

(more than one answers)

A)  A Pool Capacity can be assigned to more than one Work Centers.
B)  A Work Center can have one or more Capacity Categories.
C)  Only one of the Capacity Categories can be assigned in the Scheduling TAB of the Work Center.
D)  Only one of the Capacity Categories can be assigned in the Costing TAB of the Work Center.
E)  An Alternative Factory Calendar can be assigned to the Capacity Category different from the Plant Factory Calendar.
.

click "1 comment" for suggested solution

Tuesday, August 11, 2020

Question no 3720 : PP Work Center

In SAP PP as at ECC6.0 EhP6, which of the following are TRUE about the PP Work Center ?

(more than one answers)

A)  More than one work center can be assigned to a cost center.
B)  More than one cost center can be assigned to a work center.
C)  Only one work center can be assigned to a cost center.
D)  Only one cost center can be assigned to a work center.
E)  Cost centers are not assigned to a work center.
.

Answers : A, D


Monday, July 13, 2020

Question no 3707 : Lead Time Scheduling

In SAP PP as at ECC6.0 EhP6, which of the following are the results of "Lead Time Scheduling" in MRP run ?

(more than one answer)

A)  Creation of Production Order.
B)  Create Capacity Load.
C)  System searches for the Routing first before settling for time data in the Material Master.
D)  Creation of a Planned Order with BOM and Routing data.
E)  Perform Source Determination.
.

click "1 comment" for suggested solution


Wednesday, September 18, 2019

Question no 3661 : Cumulative Capacity Requirement

In SAP PP as at ECC6.0 EhP6, which of the following allows views of Capacity Requirements for multiple Work Centers ?

(only one answer)

A)  Work Center Hierarchy.
B)  Work Center Grouping.
C)  Work Center Structure.
D)  Work Center Link.
E)  Work Center List.
.

Answer: A

Tuesday, August 28, 2018

Question no 3588 : Capacity Calculation controls

In SAP PP as at ECC6.0 EhP6, which of the following will have an impact on Capacity calculation for an operation in a Production Order ?

(more than one answers)

A)  In-house production time (material master MRP 2 view)
B)  Operation Control Key (Routing operation)
C)  Queue time (Work Center)
D)  Standard values (Routing operations)
E)  Goods Receipt processing time (material master MRP 2 view)
.

Answer: B, D

A) In-house production time is used for MRP Basic scheduling where the system never looks for a Routing. This time parameter is only for MRP run, when converting a Planned Order to Production Order or manually creating a Production Order; the system will never use this time parameter.
B) Operation Control Key has a configuration that decides if Capacity will be calculated.
C) Queue time and Wait time from the Work Center default to the Operation in the Routing are inter-operation times. 
D) Standard values defined in the work center and later entered in the Operation in the Routing, together with the Formula will result in the Capacity Load.
E)  GR processing time is not used for "Scheduled Dates" but only for MRP run or for "Basic Dates".

Sunday, August 26, 2018

Question no 3587 : Capacity Load in Production Order

In SAP PP as at ECC6.0 EhP6, select the time parameters can do not affect the calculation of capacity load for work center of an operation in a production order ?

(more than one answers)

A)  Setup time.
B)  Processing time.
C)  Wait time.
D)  Move time.
E)  Queue time.
.

Answer: C, D, E

Wait, Move, Queue are all inter-operation times with no impact on capacity loads of the work center.

Sunday, May 1, 2016

Question no 3138 : Time segments for Capacity Load

In SAP PP as at ECC6.0 EhP6, which of the following time segments directly affects capacity requirement / capacity load calculations ? 

(more than one answers)

A)   Setup times.
B)   Transport time.
C)   Move time.
D)   Operation Control key.
E)   In-house Production time (Material Master).
.

Sunday, February 22, 2015

Question no 2606 : Reduction Strategy (PP)

In SAP PP (ECC6 EhP6), which of the following time elements can be included in the Reduction Strategy during scheduling ?

(A)   Setup time.
(B)   Teardown time.
(C)   Queue time.
(D)   Wait time.
(E)   Move time.
.

Thursday, July 17, 2014

SAP PP Available Capacity Calculation

In SAP PP, the following is a Labor Work Center, based on the Work Center data and the Routing presented, what do you think is the Capacity Load if the Production Order is 200 pc ?






(only one answer)

A)    200.0 hours.
B)    180.0 hours.
C)    162.0 hours.
D)    222.2 hours.
E)    246.9 hours.
.

SAP PP Available Capacity Calculation

In SAP PP, review the following setup and determine the Available Capacity ?




(only one answer)

A)    80.0 hours
B)    72.0 hours
C)    64.8 hours
D)    65.6 hours
E)    92.0 hours
.

Thursday, September 6, 2012

Question no 1663: PP Work centers

In SAP ECC6.0 PP, which of the following statements are true about PP work centers ?

(more then one answers)

A)    More then one PP work center can be assigned to one cost center.
B)    The formulas for capacity calculation and scheduling need to be the same.
C)    More then one capacity categories are allowed for each PP work center.
D)    Implementing shift sequence in a PP work center is optional.
E)    A PP work center must use the same factory calendar from the Plant the work center is created.
.

Saturday, February 5, 2011

Question no 951 : PP Work center

In SAP PP, a production environment using SAP wish to create 3 common packing lines as separate work centers but wish to maintain only one capacity category as the packing labors are shared among the 3 packing lines; what would you suggest ?

(select the best single answer)

A)     Capacity Hierarchy.
B)     Capacity Category.
C)     Pool Capacity.
D)     Grouped Capacity.
E)     Capacity Version.
.

Saturday, August 28, 2010

Question no : 421 PP Master Data Work Center

TERP10 Quiz Unit 06 Manufacturing Execution

Assess which of the following statement is TRUE regarding the work center ? 
.
I)      A work center is created a the plant level.
II)     A work center can be created without a plant if it is used across multiple plants.
III)    A work center can be linked one or more cost centers and activity types.
IV)    A work center can be linked to only one cost center but more then one activity types.

A)     I, III.
B)     II, IV.
C)     I, IV. 
D)     II, III.
E)     I only. 
. 

Question no : 420 PP Master Data Capacity Calculation

TERP10 Quiz Unit 06 Manufacturing Execution

Calculate the availability capacity based on the following work center capacity data ?   
    start time is 09:00
    finish time is 19:00
    break time is 2 hours
    number of capacity is 5 units
    efficiency 90%

A)     45 hours.
B)     36 hours.
C)     40 hours.
D)     48 hours.
E)     54 hours.
.