Question no 3169 : Hierarchy in SAP Maintenance Planning

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following Maintenance Plan scenario do not allow the use of Hierarchy ?

(more than one answers)

A)   Single Cycle Plan.
B)   Time-Based Strategy Plan.
C)   Performance-Based Strategy Plan.
D)   Mutli-Counter Plan.
E)   External Services Plan.

Tuesday, July 10, 2012

Question no 1611: Hierarchy of Maintenance Package

In SAP ECC6.0, deduce the scheduling results of the following Strategy Plan Setup ?

Maintenance Package (1M) : Hierarchy 1
Maintenance Package (6M) : Hierarchy 1
Maintenance Package (12) : Hierarchy 2

Maintenance Task List has the following operations and Package assignment
----------------------1M----6M----12
Operation 10------X-----X-----X
Operation 20------X-----X
Operation 30--------------------X
(the above illustration may not be correctly aligned)
Package 1M, 6M, 12 are assigned to Operation 10
Package 1M, 6M are assigned to Operation 20
Package 12 is assigned to Operation 30

When the Maintenance Plan is schedule, at Package 6M, how will be maintenance order be created ?

(only one answer)

A) Operation 10 only.
B) Operation 10, 20.
C) Operation 10, 20, 30.
D) Operation 10, 10, 30.
E) Operation 10, 30.
.

Monday, July 9, 2012

Question no 1610: Hierarchy of Maintenance Package

In SAP ECC6.0, deduce the scheduling results of the following Strategy Plan Setup ?

Maintenance Package (1M) : Hierarchy 1
Maintenance Package (6M) : Hierarchy 1
Maintenance Package (12) : Hierarchy 2

Maintenance Task List has the following operations and Package assignment
----------------------1M----6M----12
Operation 10------X-----X-----X
Operation 20------X-----X
Operation 30--------------------X
(the above illustration may not be correctly aligned)
Package 1M, 6M, 12 are assigned to Operation 10
Package 1M, 6M are assigned to Operation 20
Package 12 is assigned to Operation 30

When the Maintenance Plan is schedule, at Package 12, how will be maintenance order be created ?

(only one answer)

A) Operation 10 only.
B) Operation 10, 20.
C) Operation 10, 20, 30.
D) Operation 10, 10, 30.
E) Operation 10, 30.
.

Wednesday, April 6, 2011

Question no 1029 : Maintenance Strategy Hierarchy




The first screen shot depicts the maintenance strategy and its hiearchy and the second screen shot depicts the maintenance package setup in the maintenance task list. 

When the maintenance is due on the 12th month or 1 year, which operations will be copied to the maintenance order which is due ? 

(only one answer) 

A)     20, 30
B)     10, 10, 20, 20, 30 
C)     20, 20, 30
D)     10, 20, 20, 30 
E)     10, 20, 30 
.

Thursday, December 2, 2010

Question no : 792 PM Preventive Maintenance Plan Parameters

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which of the following parameter can be used to extend or shorten the maintenance cycle, for example, to react to temporary additional requirements without changing the maintenance strategy ?
(only one answer)

(A) Scheduling parameter.
(B) Offset.
(C) Preliminary buffer and Follow-up buffer.
(D) Call Horizon.
(E) Cycle modification factor.
.

Question no : 791 PM Preventive Scheduling

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

In scheduling the maintenance plan, the maintenance orders scheduled can be:
(more than one answers)

(A) Re-started.
(B) Skipped.
(C) Confirmed.
(D) Fixed.
(E) Called.
.

Question no : 791 PM Preventive Scheduling Control

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which of the following has the effect that the start/end dates for the order to be shifted forwards or backwards respectively with regard to the planned date.
(only one answer)

(A) Preliminary buffer and Follow-up buffer in the maintenance package.
(B) Preliminary buffer and Follow-up buffer in the maintenance plan.
(C) Offsets in the task list header.
(D) Preliminary buffer and Follow-up buffer in the task list operations.
(E) Offsets in the maintenance package.
.

Question no : 790 PM Preventive Time-Based Characteristics

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which of the following is true about Time-Based Strategy Maintenance Planning ?
(more than one answers)

(A) The maintenance task list header must be assigned with a Maintenance Strategy.
(B) Only general task list can be used for this type of Strategy Plan.
(C) The Strategy assigned to the Task list must be the same strategy in the Maintenance Plan.
(D) The Call Horizon is not applicable for this type of Maintenance Plan.
(E) All counters for the same task list must have the same Maintenance Strategy.
.

Question no : 789 PM Preventive Task List in Time-Based Plan

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

To prepare the task list to be used as Time-Based Strategy Maintenance Plan, you will:
(only one answer)

I   Assign the time-based strategy plan to the task list header.
II  Assign the time-based strategy plan to the technical objects.
III Assign the maintenance packages to the task list header.
IV Assign the maintenance packages to the respective operations.
V   Assign the maintenance packages to the technical objects.

(A) II, V
(B) I, V
(C) II, III
(D) II, IV
(E) I, IV
.

Question no : 788 PM Preventive Maintenance Package

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which data element you have to set to ensure a package is executed only once from the maintenance package ?
(only one answer)

(A) SF later confirmation = 100%.
(B) Call Horizon.
(C) Offset.
(D) SF later confirmation = 0%.
(E) Tolerance (+) for SF = 0%.
.

Question no : 787 PM Preventive Maintenance Package characteristics

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Each maintenance package contain the following characterization:
(more than one answers)

(A) Maintenance package number.
(B) Cycle length.
(C) Hierarchy.
(D) Offset.
(E) Cycle unit.
.

Question no : 786 PM Preventive Hierarchy in Maintenance Package

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

The hierarchy of maintenance packages defines how maintenance packages are to be executed:
(more than one answers)

(A) If maintenance packages have different hierarchy levels, the maintenance package with the higher level will determine which operations will be included in the called object.

(A) If maintenance packages have different hierarchy levels, the maintenance package with the lower level will determine which operations will be included in the called object.

(C) If maintenance packages have different hierarchy levels, the maintenance package with the lower level always ignored.

(D) If maintenance packages with the same hierarchy level coincide, these maintenance packages are executed together.

(E) If maintenance packages have different hierarchy levels, the maintenance package with the lower level may include the operations depending on the setup in the maintenance package rules.
.