This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label SCM520 Unit 05 Release Strategy. Show all posts
Showing posts with label SCM520 Unit 05 Release Strategy. Show all posts

Wednesday, June 5, 2013

Question no 1934 : Release Strategy

In SAP MM ECC6.0, each person who is involve in "releasing" a purchasing document in the activated release strategy is assigned with a ____________ .

(only one answer)

(A)   Release strategy
(B)   Release point.
(C)   Release code.
(D)   Release node.
(E)   Release identity.

Monday, October 22, 2012

Question no 1706 : Overall Release

In SAP MM ECC6.0, which of the following purchasing documents allows "Overall Release" for the Release Strategy ?

(more then one answers)

A)    Purchase Requisition.
B)    RFQ.
C)    Purchase Order.
D)    Contract.
E)    Scheduling Agreement.
.

Wednesday, April 11, 2012

Question no 1543 : Purchase Requisition Field Selection

In SAP MM, as at ECC6.0 EhP 4.0, which of the following are the influencing factors for field selection of Purchase Requisition ?

(more then one answers)

A)    Transaction code.
B)    Release Indicator of Release Strategy.
C)    Document type.
D)    Purchasing Organization.
E)    Plant.
.

Saturday, March 24, 2012

Question no 1528 : Release Strategy without Classification

In SAP MM Purchasing, which of the following is not a criteria for Release Strategy without Classification for Purchase Requisition ?

(only one answer)

A)   Currency code.
B)   Material group.
C)   Plant.
D)   Account Assignment.
E)   Item category.
.

Friday, March 23, 2012

Question no 1527 : Release Strategy

In SAP MM up to ECC6.0 Extension set 2, which of the following is TRUE about Release Strategy in MM Purchasing Document usage ?

(more then one answers)

A)    Item-level Release Strategy is only relevant for Purchase Requisition.
B)    The class type for Release strategy for all Purchasing document types is the same.
C)    Each Purchasing document type has its own communication table for reference characteristics creation.
D)    Maximum Release codes in a Release Strategy for Purchase Requisition is 8.
E)    The field selection key is assign to the Release Indicators.
.

Monday, October 10, 2011

Question no 1402 : Release Strategy

In SAP MM, which of the following documents can be subjected to Release Strategy ?

(more then one answers)

A)     RFQ.
B)     Scheduling Agreements Delivery Schedules Releases.
C)     Service Entry Sheet.
D)     Purchase Requisition.
E)     Planned Order for Purchasing.
.

Thursday, July 14, 2011

Question no 1161 : Release Strategy Characteristics

In SAP MM, the Release Indicator for Purchase Requisitions contains which of the following characteristics ?

(more then one answers)

A)     A Release Indicator may or may not be assigned a Field Selection Key.
B)     A Release Indicator can be set with either "Released for Quotation" or "Released for issue of PO".
C)     A Release Indicator can be set with both "Released for Quotation" or "Released for issue of PO".
D)     A Release Indicator can be set with "Release for Printing".
E)      When a Release Indicator is created, it is not Release Group dependent.
.

Question no 1160 : Release Strategy without Classification

In SAP MM, which of the following are not a fixed criteria for Release Strategy without Classification for Purchase Requisition ?

(more then one answers)

A)    Account Assignment Categoy.
B)     Item Category.
C)     Plant.
D)    Purchasing Organization.
E)     Value of Purchase Requisition.
.

Question no 1159 : Release Strategy Characteristics

In SAP MM, which of the following are true regarding Release strategy ?

(more then one answers)

A)     Both Header and item Release strategy are possible for Purchase Requisitions.
B)     Each Purchase Requisition document type may have only either Header or item level Release Strategy but not both.
C)     The configuration for item level Release Strategy for Purchase Orders are set at the item category level.
D)     The class type use to classify criteria for Purchase Requisition and Purchase Order is the same class type.
E)      A user can be assigned with multiple release codes for the authorization profiles
.

Question no 1158 : Release Strategy Characteristics

In SAP MM, which of the following are the correct configuration characteristics of Release Strategy ?

(more then one answers)

A)   The maximum release code per Release Strategy is 8.
B)    The Release Prerequisite depends on how many release codes are assigned to the Release Strategy.
C)    A Release group contain multiple Release Strategy.
D)    Each Release group can be assigned with only one Class for Classifications of the criteria.
E)    The Release group are always plant dependent.
.

Question no 1157 : Release Strategy class type

In SAP MM, which class type is used for Release Strategy ?

(only one answer)

A)     12.
B)      22.
C)      32.
D)      42.
E)      43.
.

Monday, March 7, 2011

Question no 998 : Field Selection for Purchasing Document

In SAP MM, in order to control the field selection during Release Strategy Processes; this can be achieved via which of the following configuration parameters ?

(only one answer)

A)      Item category.
B)      Document type.
C)      Transaction.
D)      Price display authorization.
E)      Release Status
.

Saturday, September 5, 2009

Question no : 195 MM Purchasing Release Strategy

Which class type is used for Release Strategy ?

A)  001.
B)  023.
C)  032.
D)  300.
E)  320.
.

Thursday, September 3, 2009

Question no : 194 MM Purchasing Release Strategy

Which of the following purchasing document allow either Overall or Item level Release Strategy ?

A)   Purchase Requisition.
B)   Purchase Order.
C)   RFQ.
D)   Contract.
E)   Scheduling Agreement.
.

Sunday, March 1, 2009

Question no : 110 MM Purchasing Release Strategy

Which of the following purchasing document's release strategy is at the item level ?

A)    Purchase Requisition.
B)    Purchase Order.
C)    RFQ.
D)    Contract.
E)    Scheduling Agreement.
.