Question no : 790 PM Preventive Time-Based Characteristics

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which of the following is true about Time-Based Strategy Maintenance Planning ?
(more than one answers)

(A) The maintenance task list header must be assigned with a Maintenance Strategy.
(B) Only general task list can be used for this type of Strategy Plan.
(C) The Strategy assigned to the Task list must be the same strategy in the Maintenance Plan.
(D) The Call Horizon is not applicable for this type of Maintenance Plan.
(E) All counters for the same task list must have the same Maintenance Strategy.
.