Question no : 789 PM Preventive Task List in Time-Based Plan

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

To prepare the task list to be used as Time-Based Strategy Maintenance Plan, you will:
(only one answer)

I   Assign the time-based strategy plan to the task list header.
II  Assign the time-based strategy plan to the technical objects.
III Assign the maintenance packages to the task list header.
IV Assign the maintenance packages to the respective operations.
V   Assign the maintenance packages to the technical objects.

(A) II, V
(B) I, V
(C) II, III
(D) II, IV
(E) I, IV
.