Question no : 811 PM Preventive Condition Based Scenario

PLM310 Preventive Maintenance
Unit 08 Condition-Based Maintenance

For Condition-Based Preventive Maintenance Scenario, Communication between the R/3 System and the partner system is based on:
(only one answer)

(A) PCS (Process Control System).
(B) BAPI (Business Process Interface).
(C) COMSTRCT (Communication Structure).
(D) CIF (Core-Interface).
(E) RFC (Remote Function Call).
.

Question no : 812 PM Preventive Condition-Based

PLM310 Preventive Maintenance
Unit 08 Condition-Based Maintenance

For Condition-Based Preventive Maintenance Scenario, the basis for triggering a notification in SAP when a condition is achieved is executed principally via which of the following master data element in the SAP system ?
(only one answer)

(A) RFC (Remote Function Call).
(B) Catalog codes.
(C) Breakdown condition indicator in the notification order.
(D) Measuring point.
(E) Damage code.
.

Question no : 810 PM Preventive Condition Based

PLM310 Preventive Maintenance
Unit 08 Condition-Based Maintenance

If the compressor at your company breaks down, the repair is automatically triggered by the transmission of the current condition data. For example, if a motor in the compressor breaks down, a specific malfunction code is transmitted, which triggers a corresponding notification in the PM component of the R/3 System. Which preventive maintenance scenario is applicable ?
(only one answer)

(A) Time-Based Maintenance Planning Strategy.
(B) Performance-Based Maintenance Planning Strategy.
(C) Condition-Based Maintenance Planning.
(D) Sales-of-Service-Based Maintenance Planning.
(E) Single-Cycle Maintenance Planning.
.