Unit 05 Maintenance Planning with Strategy: Performance-Based
Based on the following data, determined the expected planned start date (assuming the initial counter reading is 0) ?
(only one answer)
Estimated annual performance = 73,000 liters
Total number of days in a year = 365 days
Cycle due at = 40,000 liters
(A) in 730 days.
(B) in 365 days.
(C) in 200 days.
(D) in 100 days.
(E) in 50 days.
.
Answer: C