This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, December 5, 2010

Question no : 877 PM Execution Confirmation and System Status

PLM315 Maintenance Processing: Operational Functions
Unit 06 Completion

Which of the following confirmation results are true ?
(only one answer)

(A) Once there is a goods receipt for an external operation, but before the final delivery indicator is set, the plant maintenance order status is EODL.
(B) Once the goods receipt for an external operation is final, the plant maintenance order status is EODL.
(C) Once there is a goods receipt for an external operation, but before the final delivery indicator is set, the plant maintenance order status is EOPD.
(D) Once the external operations purchase order is invoiced, the plant maintenance order status is EOPD.
(E) Once the external operations purchase order is created, the plant maintenance order status is EODL.
.

1 comment: