Question no 4057 : Control Parameters for Production Orders

In SAP Production Planning & Execution as at S/4 1909, which of the following Parameters provides the following controls:
. BOM and Rouning selection
. Batch Determination Procedure
. Status Change Documentation
. Costing Variants for Planned and Actual Costs

(only one answer)

A)  Order Type Plant independent Parameter
B)  Order Type Plant dependent Parameter
C)  Confirmation Parameter.
D)  Production Scheduler Profile.
E)  Non of the above.
.

Answer: B

Monday, July 7, 2025

Question no 4056 : COGI in Production Orders

In SAP Production Planning & Distribution as at S/4 1909, which of the following settings will Post a Component to Post Processing record (COGI), when not enough stocks were found in the Staging Storage Location when Material was to be back-flushed during a Confirmation activity ?

I. Setup Negative Stock indicator in the Component Material Master Plant/Storage data view.
II. Setup the Plant and Storage Location in the configuration to allow Negative Stock posting.
III. Remove the "Goods Movement" Error handling indicator in the Confirmation Parameter for the Plant where the Production Order was created at.
IV. Select "COGI" indicator in the Confirmation Profile and assign the Parameter ID "AAT" to the User.
V. Set Message "M7021" as ERROR in the configuration.

(only one answer)

A) I, II, III
B) I, II, IV
C) I, II, III, V
D) IV
E) III

Answer: E

Sunday, June 22, 2025

Question no 4054 : The effects of "BOM Explosion selection methods" data field no longer available in S/4 1909

In SAP Production Planning & Execution S/4 1909, note the following MRP 4 data view the Missing "BOM Explosion selection methods" data field (no longer available) and what is the effect of this Simplification scenario for PP, considering the Production Version wasn't setup for material F5 ?



(more than one answers)

A. Production Order creation Error.
B. MD01N will not be able to perform BOM Explosion for F5
C. MD02 will plan for Material F5 based on the existing BOM.
D. Manual Planned Order will require manual entry of materials.
E. Production Order creation require manual selection of BOM.
.

Answer: A, B, D

In S/4 1909, the Material Master MRP4 data view no longer have the "BOM Explosion selection methods" data field.
Production Version is mandatory for:
. MRP run via MD02 or MDBT
. MRP run via MD01N MRP Live
. Production Order creation
. Planned Order manual creation

Wednesday, May 28, 2025

Question no 4050 : Pull List

In SAP Production Planning & Distribution, Pull List (MF60) will be able to perform staging for which of the following MRP elements ? 

(more than one answers)

A. Repetitive Planned Orders.
B. Planned Production Orders.
C. Production Orders.
D. Process Orders.
E. Stock Transfer Requirements.
.

Answer: A, B, C, D

Sunday, May 25, 2025

Question no 4049 : Stock Determination Rule for Production Order Pull List

In SAP Production Planning & Execution as at S/4 1909, the Pull list for Production Orders to Stage Components via MF60 requires the Stock Determination Rule to be assigned to which of the following ?

(only one answer)

A. Material Master.
B. Order Type Plant dependent Parameter.
C. Order Type.
D. Plant.
E. Movement Type.
.

Answer: D

Wednesday, April 16, 2025

Question no 4044 : Production Order activities before Release

In SAP Production Planning & Execution, which of the following are possible activities in a Production Order before it is Released ?

(more than one answers)

A. Costing calculation
B. Scheduling
C. Capacity determination
D. BOM and Routing determination
E. Reservation created for Components.
.

Answer: A, B, C, D, E

Wednesday, April 10, 2024

Question no 3996 : Non-Order related Replenishment

In SAP Manufacturing as at ECC6 EhP7, the transaction MF60 "Pull List" for replenishment of materials for Non-Order related replenishment for a series of Production Orders uses which of the following Control Cycle method ?
(more than one answers)

A. Crate parts.
B. Pick parts.
C. Release order parts.
D. Event-Driven Kanban.
E. Storage Location Level.
.

Answer: C

Wednesday, April 3, 2024

Question no 3995 : Pull List

In SAP Manufacturing as at ECC6 EhP7, the transaction MF60 "Pull List" can replenish for which of the following ?

(more than one answers)

A. Process Orders.
B. Production Orders.
C. Inspection Lot.
D. Network Orders.
E. Planned Orders.
.

Answer: A, B, E

Wednesday, September 6, 2023

Question no 3976 : PP objects without a Plant

In SAP Production Planning and Execution, which of the following PP object can be created without a Plant ?

(only one answer)

A. CS01 Create a Bills of Material.
B. CA01 Create a Routing.
C. MM01 Create a Material Master for Planning and Execution.
D. MD61 Create Planned Independent Requirement.
E. CO01 Create a Production Order.

Answer: A

A) A BOM can be created without a Plant which is called BOM Group, which later can be assigned to one or more Plants.
B) A Routing can be created without a Material but must have a Plant, which later the Routing can be assigned to one or more Materials.
C) The MRP view and Work Scheduling data view for Planning and Execution respectively are both at the Plant level.
D) A Planned Independent Requirement must be created for a Plant and Material.
E) A Production Order must be created for a Plant but need to have a Material.

Sunday, July 16, 2023

Question no 3974 : Leading and Dependent Orders in Manufacturing

In SAP Production Planning, ______________ represent multilevel production structures for materials produced in-house in which the manufacturing order for the highest material in the structure automatically generates manufacturing orders for the semi-finished products in the structure. The output quantity of the manufacturing orders for the semi-finished products is the quantity required for the manufacture of the highest material.

(only one answer)

A. Multi-level Production.
B. Joint Production.
C. Collective Orders.
D. Production Version.
E. Special Procurement Key.

Answer: C

Collective orders can consist of planned orders or manufacturing orders (production orders or process orders).
A collective order consists of the following:
A leading order
The leading order is the order at the highest level of the collective order. It is created to manufacture the finished product.
Dependent orders
All orders below the leading order are dependent orders. The system automatically creates the dependent orders for the leading order. Dependent orders can be subordinate to each other on multiple levels of the collective order.
Changes to higher-level orders (such as a changed order quantity or release of the order) are immediately reflected in all dependent orders when the order is saved.

Sunday, September 25, 2022

Question no 3947 : Set up Cost Collector for Production Order

In SAP ECC6 EhP8, which of the following is used to activate Cost Collect or Period based Costing for Production Order ?

(only one answer)

A) Plant Parameters.
B) Production Scheduler.
C) Production Scheduler Profile.
D) Order Type Plant dependent Parameter.
E) Material Master Work Scheduling view.
.

Answer: D

Wednesday, June 23, 2021

Question no 3854 : Process Quality Inspection for PP

In SAP PP/QM as at ECC6. 0 EhP6, which of the following settings are expected for initiating Process Quality Inspection for Production Order ?
(As at S/4 Hana 1909, same setup)

(more than one answers)

A)  Assign Inspection Point to the Routing Header.
B)  Assign Inspection Point to the Inspection Plan Header.
C)  Assign an appropriate Inspection Type to the Material Master.
D)  Activate a PP Order Type for QM.
E)  Assign Master Inspection Characteristics to he Routing Operation.
.

Answers: A, C, E

A, B) PQC uses the Routing Instead of the Inspection Plan, Inspection Point is therefore assign at the Routing.
C) Inspection Type 03
D) No specific requirement in activating QM in the PP Order Type.
E) Since it is Routing for PQC (Process Quality Control), therefore MICs are assigned to the Routing Operations.
The following are basic setup requirements:
1) Material Master QM data view assign Inspection Type 03.
2) Assign appropriate Inspection Point (eg: 150) in the Routing Header.
3) Assign appropriate Control Key (eg: PP06) to Routing Operation.
4) Assign QM Characteristics to Routing Operation with correct Sampling Procedure.
5) Set "Time" or "Quantity" related data in the Routing Operation detail.


Tuesday, January 12, 2021

Question no 3786 : MF50

In SAP PP as at ECC6.0 EhP6, the T-Code MF50 Planning Table can be used for the following ?

(more than one answers)

A)  Read "Active" Planned Independent Requirements.
B)  Show Production Order quantities.
C)  Show Make-to-Order scenario quantities.
D)  Show Make-to-Stock scenario quantities.
E)  Show capacities.
.

Answers: A, B, C, D, E

MF50 interface shows a "spreadsheet-like" tabular format to view the Planning data that can show MTO or MTS scenario data as well as Capacities data
 

Monday, January 11, 2021

Question no 3785 : Collective Production Orders

In SAP PP as at ECC6.0 EhP6, which of the following is used to activate Collective Production Orders ?

(only one answer)

A)  Special Procurement Key.
B)  Production Scheduler Profile.
C)  An indicator in the Material Master Work Scheduling data view.
D)  MRP Plant parameter.
E)  MRP Group parameter.
.

click "1 comment" to view Suggested Solution

Wednesday, December 2, 2020

Question no 3769 : Cost Collector in PP

In PP as at ECC6.0 EhP6, which of the following can use a Cost Collector to collect costs ?

(more than one answers)

A)  Repetitive Planned Orders.
B)  Planned Orders for Shop Floor Production.
C)  Production Orders.
D)  Planned Independent Requirement.
E)  Planning Scenario.
.

Click "1 comment" for possible solution.

Tuesday, June 16, 2020

Question no 3699 : Time Based Floats

In SAP PP as at ECC6.0 EhP7, which of the following are examples of Time Based Floats in an MRP run and Production Order creation ?

(more than one answers)

A)  Safety Time.
B)  Safety Stock.
C)  Dynamic Safety Stock.
D)  Float Before Production.
E)  Float After Production.
.

click (1 comment) for suggested answers

Wednesday, May 13, 2020

Question no 3694 : Production Order features and functions

In SAP PP as at ECC6.0 EhP6, which of the following are not possible for PP Production Order ?

(more than one answers)

A)  Production Campaign.
B)  PP Sheet. (similar to PI sheet)
C)  Use of Production Version.
D)  Backflushing.
E)  CATS entry for Confirmation.
.

click "1 comment" for suggested answers

Sunday, August 26, 2018

Question no 3587 : Capacity Load in Production Order

In SAP PP as at ECC6.0 EhP6, select the time parameters can do not affect the calculation of capacity load for work center of an operation in a production order ?

(more than one answers)

A)  Setup time.
B)  Processing time.
C)  Wait time.
D)  Move time.
E)  Queue time.
.

Answer: C, D, E

Wait, Move, Queue are all inter-operation times with no impact on capacity loads of the work center.

Monday, October 3, 2016

Question no 3296 : Production Order creation

In SAP PP as at ECC6.0 EhP6, a Production Order can be created with which of the following options ?

(more than one answers)

A)  Without Material.
B)  Without Routing.
C)  Without Plant.
D)  Without BOM.
E)  Without a Work Center.
.

Question no 3290 : Collective Producton Orders

In SAP PP as at ECC6.0 EhP6, the Collective Production Order scenario can be set via which of the following ?

(more than one answers)

A)  Special Procurement key in the Material Master MRP 2 data view.
B)  Item Category in the Bill of Material.
C)  BOM Item detail.
D)  BOM Header.