Question no : 856 PM Execution Order Hierarchy

PLM315 Maintenance Processing: Operational Functions
Unit 03 Planning

When maintenance orders are maintenance in a order hierarchy linking various maintenance orders in a hierarchy:
(more than one answers)

(A) All sub-orders must be completed before the main maintenance order.
(B) There are no costs collected at the sub-orders, all costs are only collected a the main order.
(C) All sub-maintenance orders must be confirmed before the main maintenance order is confirmed.
(D) The planner for the leading order bears the responsibility for executing all the lower level orders.
(E) The leading orders provide proposals of the basic dates for the lower-level orders.
.