Question no : 868 PM Execution Operation Relationship

PLM315 Maintenance Processing: Operational Functions
Unit 04 Scheduling

The 2 operations in the maintenance order are to be started at the same time, it should have the following relationship:
(only one answer)

(A) FF
(B) SF
(C) FS
(D) SS
(E) FF
.