Question no : 793 PM Preventive Strategy Choice

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

If a inspection/safety check should be performed after 15,000 litres and all the seals changed after 200,000 liters, which of the following Preventive maintenance strategy is recommended ?
(only one answer)

(A) Time-Based Maintenance Planning Strategy.
(B) Performance-Based Maintenance Planning Strategy.
(C) Condition-Based Maintenance Planning.
(D) Sales-of-Service-Based Maintenance Planning.
(E) Single-Cycle Maintenance Planning.
.