This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label Test : Project System. Show all posts
Showing posts with label Test : Project System. Show all posts

Monday, October 3, 2016

Question no 3299 : Project System Structure Assignments

In SAP PS as at ECC6.0 EhP6, which of the following assignments in PS are correct ?

(more than one answers)

A)  more than one network structure can be assign to one Operative Project.
B)  one of more network activities can be assign to a WBS.
C)  activities from more than one network structure an be assign to a WBS.
D)  a project cannot be saved without a network structure.
E)  one or more project definition can exist in a Project structure.
.

Question no 3298 : Key Profile when creating Project

In SAP PS as at ECC6.0 EhP6, which of the following is the key Profile use to create Template/Standard and Operative Project Definition and WBS ?

(only one answer)

A)  Project Definition.
B)  Settlement Profile.
C)  Default Profile.
D)  Project Profile.
E)  User Parameter Profile.
.

Tuesday, September 14, 2010

Question no : 481 PS Master Data Basics

TERP10 (Unit 10) Program and Project Management 
.
A useful tool in SAP PS which allows you to efficiently edit and access your project is the _______________ . 
   
(Select ONE best answer)

A)   Easy cost planning.
B)   Manager's desktop.
C)   Work Breakdown structure. 
D)   Project builder. 
E)    Engineering workbench.

Question no : 480 PS Accounting Scenario

TERP10 (Unit 10) Program and Project Management 
.
Which of the following tools in the SAP PS allows your to easily plan costs by cost element in a quantity structure and then use the execution services to enter commitment and actual data for the planned costs ? 
   
(Select ONE best answer)

A)   Easy Cost Planning.
B)   Budgeting. 
C)   Cost estimate. 
D)   Unit costing. 
E)    Manager's Desktop.