Unit 04 Maintenance Planning with Strategy: Time-Based
Which of the following has the effect that the start/end dates for the order to be shifted forwards or backwards respectively with regard to the planned date.
(only one answer)
(A) Preliminary buffer and Follow-up buffer in the maintenance package.
(B) Preliminary buffer and Follow-up buffer in the maintenance plan.
(C) Offsets in the task list header.
(D) Preliminary buffer and Follow-up buffer in the task list operations.
(E) Offsets in the maintenance package.
.