This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label PLM300 Unit 04 Breakdown Maintenance. Show all posts
Showing posts with label PLM300 Unit 04 Breakdown Maintenance. Show all posts

Saturday, March 12, 2011

Question no 1008 : Maintenance order technical completion

In SAP PM, when a maintenance order to technically completed, it may also be closing the notification provided that ______________________ .

(only one answer)

A)      All the task and activities are also set to be completed.
B)      All the activities are completed.
C)      There is no breakdown indicator in the maintenance notification.
D)      All the tasks are completed.
E)      The Notification type allows completion via technical completion of a maintenance order.
.

Friday, March 11, 2011

Question no 1007 : Maintenance Order-Notification

In SAP PM, when a break-down maintenance order is to be created, it should also automatically generated a maintenance notification when the order is saved. Which of the following parameter is used to achieve this scenario ?

(only one answer)

A)      Notification type at Client level.
B)      Notification type at Plant level.
C)      Order type at Client level.
D)      Order type at Plant level.
E)      User exit.
.

Question no 1006 : Maintenance Notification System Status

In SAP PM Notification, if the Notification has the following status ATCO and ORAS; this would mean which of the following ?

(only one answer)

A)     Task Outstanding and Order Completed.
B)     All Task Completed and Order Completed.
C)     All Task Completed and Order Assigned.
D)     Task Outstanding and Order Assigned.
E)     Task Outstanding and Order Technically Completed.
.

Thursday, October 21, 2010

Question no : 594 PM Execution Order Put in Process

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

A maintenance order can be put in process, which of the following are the results of this processing step ?
(more than one answers)

(A) The maintenance order shop papers are not printed automatically.
(B) The maintenance order shop papers are printed automatically.
(C) The maintenance order is released.
(D) The maintenance order is costed and saved.
(E) The maintenance order is settled.
.

Question no : 593 PM Execution Order TECO

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

At technical complete of the maintenance order, which data is transferred from the maintenance order to the notification ?
(only one answer)

(A) Malfunction start date.
(B) Malfunction end date.
(C) Cause code.
(D) Damage code.
(E) Activities.
.

Wednesday, October 20, 2010

Question no : 592 PM Execution Order Breakdown Concepts

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

In General, the minimum data requirement for the maintenance order creation is:
(more than one answers)

(A) Maintenance order type.
(B) A technical object.
(C) Priority.
(D) Short text.
(E) Spare parts.
.

Question no : 591 PM Execution Order Breakdown Processing Options

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Which of the following processing options are possible the for Breakdown Maintenance scenario ?
(more than one answers)

(A) Completing the notification while technically completing the maintenance order.
(B) Completing the notification separately from the technical completion of the maintenance order.
(C) Partially confirmation of the notification.
(D) Partially confirmation of the maintenance order.
(E) Partially confirmation of the maintenance order’s operations.
.

Question no : 590 PM Execution Order Confirmation Options

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Which confirmation options are available for Breakdown maintenance execution and completion ?
(more than one answers)

(A) Individual entry.
(B) Collective entry.
(C) Collective entry using operation list.
(D) Overall completion confirmation.
(E) Progress confirmation.
.

Tuesday, October 19, 2010

Question no : 589 PM Execution Order Partial Confirmation

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Partial confirmation with the status “PCNF” status in Time Confirmation option allows which of the following process ?
(more than one answers)

(A) Partial Confirmation done can be partially reversed.
(B) Partial Confirmation done must be reversed in full.
(C) Full Confirmation “CNF” can be done in the following confirmation step.
(D) Additional costs can be posted but the account assignment data is fixed.
(E) Account assignment data is changeable but additional costs cannot be posted.
.

Question no : 588 PM Execution Order TECO

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Technical completion of the maintenance order has the following effect ?
(more than one answers)

(A) Only certain fields in the maintenance order can now be changed.
(B) The “TECO” technically complete status can be revoked.
(C) Additional costs cannot be posted.
(D) Additional costs can be posted but the account assignment data is fixed.
(E) Allow immediate archiving and deletion of the maintenance order.
.

Question no : 587 PM Execution Order Overall Confirmation

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Overall confirmations can be used to process which of the following processes ?
(more than one answers)

(A) Goods issue.
(B) Counter readings.
(C) Causes and activities for the notification order.
(D) Measurement readings.
(E) Time data.
.

Question no : 586 PM Execution Breakdown Scenario

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

As a breakdown maintenance order can be created with or without a notification OR a notification is created with an a breakdown maintenance order. Which data element controls or provides these possibilities ?
(only one answer)

(A) Selection function in the Maintenance order initial screen.
(B) Maintenance order and Notification order link.
(C) Notification order type.
(D) Maintenance order scenario.
(E) Maintenance order type.
.

Monday, October 18, 2010

Question no : 585 PM Execution Order Release

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

What activities are possible after a maintenance order has been released ?
(more than one answers)

(A) Material issue.
(B) Enter time confirmations.
(C) Post goods receipts.
(D) Completing a tasks.
(E) Printing shop papers.
.

Question no : 584 PM Execution Order Put in Process

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

The function of put in process does which of the following ?
(only one answer)

(A) Releases the order, prints the required order papers, and finally saves the order.
(B) Releases the order and prints the required order papers.
(C) Releases the order and saves the order.
(D) Releases the order, prints the required order papers, creates the necessary material or spare parts reservations, and finally saves the order.
(E) Release the order, prints the required order papers, creates spare parts reservations, perform availability check, and finally saves the order.
.

Sunday, October 17, 2010

Question no : 583 PM Execution Notification-Order interfaces

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

Select the True statements about Maintenance Notification and Maintenance Orders ?
(more than one answers)

(A) Maintenance Notification is a required pre-requisite step for maintenance order creation.
(B) Maintenance order creation can be created directly without any Maintenance notifications.
(C) Maintenance notifications created must follow up with a maintenance order or it cannot be closed.
(D) Maintenance notifications created may be independent of maintenance orders.
(E) If a Maintenance notifications does not exist, it can be generated via the Maintenance order.
.

Question no : 582 PM Execution Breakdown Scenario

PLM300 Plant Maintenance
Unit 04 Breakdown Maintenance

The Breakdown Maintenance Process is characterized by ….
(only one answer)

(A) Notification, Planning, Capacity Planning, Execution, Completion.
(B) Notification, Planning, Scheduling, Capacity Planning, Execution, Completion.
(C) Notification, Scheduling, Capacity Planning, Execution, Completion.
(D) Notification, Scheduling, Execution, Completion.
(E) Notification, Order generation and release, Execution, Completion.
.