Monday, July 7, 2025

Question no 4056 : COGI in Production Orders

In SAP Production Planning & Distribution as at S/4 1909, which of the following settings will Post a Component to Post Processing record (COGI), when not enough stocks were found in the Staging Storage Location when Material was to be back-flushed during a Confirmation activity ?

I. Setup Negative Stock indicator in the Component Material Master Plant/Storage data view.
II. Setup the Plant and Storage Location in the configuration to allow Negative Stock posting.
III. Remove the "Goods Movement" Error handling indicator in the Confirmation Parameter for the Plant where the Production Order was created at.
IV. Select "COGI" indicator in the Confirmation Profile and assign the Parameter ID "AAT" to the User.
V. Set Message "M7021" as ERROR in the configuration.

(only one answer)

A) I, II, III
B) I, II, IV
C) I, II, III, V
D) IV
E) III

Answer: E

Saturday, June 28, 2025

Question no 4055 : Reference Operation Sets

In SAP Logistics as at S/4 1909, Reference Operation Sets can be used for which of the following ?

(more than one answers)

A. Assign to Production Routing.
B. Assign to Production Rate Routing.
C. Assign to Inspection Plan.
D. Assign to Material Specifications.
E. Assign to General Maintenance Task List.
.

Answer: A, B, C

As at S/4 1909, Reference Operation Sets are used in:
. PPDI Production Routing
. PPDI Repetitive Rate Routing
. QM Inspection Plan

Sunday, June 22, 2025

Question no 4054 : The effects of "BOM Explosion selection methods" data field no longer available in S/4 1909

In SAP Production Planning & Execution S/4 1909, note the following MRP 4 data view the Missing "BOM Explosion selection methods" data field (no longer available) and what is the effect of this Simplification scenario for PP, considering the Production Version wasn't setup for material F5 ?



(more than one answers)

A. Production Order creation Error.
B. MD01N will not be able to perform BOM Explosion for F5
C. MD02 will plan for Material F5 based on the existing BOM.
D. Manual Planned Order will require manual entry of materials.
E. Production Order creation require manual selection of BOM.
.

Answer: A, B, D

In S/4 1909, the Material Master MRP4 data view no longer have the "BOM Explosion selection methods" data field.
Production Version is mandatory for:
. MRP run via MD02 or MDBT
. MRP run via MD01N MRP Live
. Production Order creation
. Planned Order manual creation

Wednesday, May 28, 2025

Question no 4050 : Pull List

In SAP Production Planning & Distribution, Pull List (MF60) will be able to perform staging for which of the following MRP elements ? 

(more than one answers)

A. Repetitive Planned Orders.
B. Planned Production Orders.
C. Production Orders.
D. Process Orders.
E. Stock Transfer Requirements.
.

Answer: A, B, C, D

Sunday, May 25, 2025

Question no 4049 : Stock Determination Rule for Production Order Pull List

In SAP Production Planning & Execution as at S/4 1909, the Pull list for Production Orders to Stage Components via MF60 requires the Stock Determination Rule to be assigned to which of the following ?

(only one answer)

A. Material Master.
B. Order Type Plant dependent Parameter.
C. Order Type.
D. Plant.
E. Movement Type.
.

Answer: D

Wednesday, April 16, 2025

Question no 4044 : Production Order activities before Release

In SAP Production Planning & Execution, which of the following are possible activities in a Production Order before it is Released ?

(more than one answers)

A. Costing calculation
B. Scheduling
C. Capacity determination
D. BOM and Routing determination
E. Reservation created for Components.
.

Answer: A, B, C, D, E

Thursday, March 6, 2025

Question no 4038 : Where can Forecasting run be executed

In SAP PP or MM Forecasting as at S/4 1909, Forecasting Run can be executed in which of the following ?

(more than one answers)

A. When creating a Planned Independent Requirement.
B. When creating a Material Sales & Operations Plan.
C. In the Material Master in the Forecasting data view.
D. Interactively when creating a Long Term Planning Scenario.
E. When creating a Product Group Sales & Operations Plan.
.

Answer: A, B, C

A) In MD61, the Forecasting results done in Material Master Forecasting view OR MP30 can be copied to the PIR quantities. In additional, user can perform Forecasting run based on Consumption History to generate the PIR quantities here in MD61. 


B) In MC87, Material SOP Plan can execute Interactive Forecasting to generate the planning quantities.


C) Material Master Forecasting data view do have a Forecasting facility.


D) LTP scenario does not have any Forecasting tools.


E) In MC81 for Product Group SOP Plan, the menu do provide access to the Forecasting but it will read "Error reading Consumption data" (Message MA518)

Friday, February 28, 2025

Question no 4037 : "Planning Time Fields" in Advanced Planning

In SAP Production Planing as at S/4 1909, which of the following "Planning Time fields" are valid ?

(more than one answers)

A. Plant Parameter Planning Horizon.
B. MRP Group Parameter Planning Horizon.
C. MRP 1 view Time Fence.
D. PPDS Planning Horizon.
E. SNP Horizon.
.

Answer: C, D

A, B) The Classic Planning Horizon in Plant Parameter (OPPQ) and MRP Group (OPPR) no longer available.
C) Planning Time Fence in MRP 1 view is still valid which effectively seen in MD04 and APO Product view.
D) PPDS Horizon can be set for each Advanced Planning Version.
E) The APO SNP module is not yet available in S/4 1909.

Monday, January 27, 2025

Question no 4033 : PDS Transfer via CURTOADV_CREATE

In SAP Advanced Planning S/4 1909, which of the following are TRUE for PDS Transfer via CURTOADV_CREATE ?

(more than one answers)

A. A Production Version must be created for the Materials concerned.
B. The Production Version must have a valid Routing and a valid BOM.
C. The Production Version can be with a valid BOM and without Routing.
D. The Assembly must have an Advanced Planning view but MRP views are not necessary in the Material Master.
E. Only Target Version "000" Active Version can be transferred.
.

Answer: A, C

A) If a valid BOM with its components were to be transferred to Advanced Planning, not just just assembly but the components must have been activated for Advanced Planning before executing CURTOADV_CREATE.
B, C) As at 1909, A Production Version must exist but only a BOM is necessary and Routing is not mandatory for a successful PDS Transfer.
D) When activating a Material for Advanced Planning, MRP view becomes Mandatory.
E) Target Version other than "000" can be transferred.


Tuesday, December 17, 2024

Question no 4028 : Advanced Planning MRP Types

In SAP Production Planning & Detail Scheduling, which of the following MRP Types are allowed for "Advanced Planning" in S/4 1909 ?

(More than one answers)

A. PD
B. VB
C. X0
D. M0
E. R1
.

Answer: A, B, D, E

Basically, MRP Type "X0" used to be for when APO was a separate entity (system), now in S/4; PPDS runs recognizes MRP Types with Procedure "MRP, "MPS", and "CBP".

Sunday, July 21, 2024

Question no 4009 : Splitting requirement quantity to Supplier or Production Version based on the Quota

In SAP MRP Planning as at ECC6 EhP8, which of the following Lot Size key is recommended to always split the requirements between Suppliers or Production Versions based on the Quota entered for the Supplier or Production Versions in the Quota Arrangement ?

(only one answer)

A. EX
B. ES
C. FX
D. FS
E. SP
.

Answer: B

"ES" Lot for Lot with Split
The same functionality is available as in the current S/4HANA2023 version.



Monday, June 3, 2024

Question no 4002 : Stock Requirement List features

In SAP Production Planning & Execution as at ECC6 EhP8, which of the following feature in MD04 provides an avenue to perform configuration for transaction call ?

(only one answer)

A. Navigation Profile.
B. User Setting.
C. MRP Profile.
D. Requirements Grouping.
E. Not possible.

Answer: A

You can use the "general" navigation profile to insert additional functions or transactions into the application toolbar or context menu of an ALV grid control or ALV tree control. You can create, change, save, and manage user-specific and non user-specific navigation profiles. In navigation profiles, you can define which functions, transactions, class calls, or menus are displayed in the application toolbar or context menu. You can also transport or import navigation profiles.







Saturday, April 20, 2024

Question no 3997 : Product Structure Browser

In SAP PLM Product Structure Browser CC04, object structure can be viewed are which of the following ?

(more than one answers)

A. Functional Location Hierarchy.
B. Equipment Hierarchy.
C. Routing.
D. Recipe.
E. Project Structure.
.

Answer: A, B, C

The Product Structure Browser can display the following:
Materials Management: Material
Document Management System (DMS): Document info record
Engineering Change Management (ECH): Change master record
Production (Master Data): BOM, Routings, Reference operation sets
Class System: Characteristic, Class
Plant Maintenance: Equipment, Functional location








Wednesday, April 10, 2024

Question no 3996 : Non-Order related Replenishment

In SAP Manufacturing as at ECC6 EhP7, the transaction MF60 "Pull List" for replenishment of materials for Non-Order related replenishment for a series of Production Orders uses which of the following Control Cycle method ?
(more than one answers)

A. Crate parts.
B. Pick parts.
C. Release order parts.
D. Event-Driven Kanban.
E. Storage Location Level.
.

Answer: C

Wednesday, April 3, 2024

Question no 3995 : Pull List

In SAP Manufacturing as at ECC6 EhP7, the transaction MF60 "Pull List" can replenish for which of the following ?

(more than one answers)

A. Process Orders.
B. Production Orders.
C. Inspection Lot.
D. Network Orders.
E. Planned Orders.
.

Answer: A, B, E

Saturday, March 30, 2024

Question no 3994 : Pull List in Manufacturing

In SAP Production Planning & Execution integration with the WM system in ECC6 EhP8, which of the following depicts Pull list based on each Production/Process Order in a WM Warehouse System"
(only one answer)

A. Crate parts.
B. Pick parts.
C. Release order parts.
D. Event-Driven Kanban.
E. Storage Location Level.
.

Answer: B

A. Crate Parts are replenished using "Kanban Containers" and not via the Pull list.
B. Pick Parts are Pull list to pick parts based on each Production/Process order.
C. Release Order Part are picked based on a range of Production/Process order where the picking results is a total quantity.