This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Showing posts with label Test : Plant Maintenance - Organization. Show all posts
Showing posts with label Test : Plant Maintenance - Organization. Show all posts

Monday, January 17, 2022

Question no 3912 : Planning Plant in Plant Maintenance

In SAP PM as at ECC6.0 EhP6, which of the following are mandatory for a Planning Plant ?

(more than one answers)

A)  General Maintenance Task List.
B)  Maintenance Notification.
C)  Maintenance Order.
D)  Permit Master.
E)  Catalog Profile.
.

Answers: A, C

Both D) Permit Master and E) Catalog Profile when created is without any Enterprise Structure definition (in this case not linked to any Plant). 

As for B) for Maintenance Notification creation, if an EQ or FL is entered, the system will locate the Planning Plant and Planner Group set in the Technical Objects but even if Planning Plant and Planner Group is not found; the Notification can be saved with BLANK Planning Plant and Planner Group.

The answers are:
A) General Maintenance Task List header requires a Planning Plant.
C) MO header initial screen requires a Planning Plant.

There are 2 types of Plant concept for Plant Maintenance:
Logistics Plant - to identify spare parts Storage
Maintenance Plant - to identify location of Technical Object, to identify the Work Center
Maintenance Planning Plant - the Logistics Plant is to have the behavior as a Planning Plant

The following is the Enterprise Structure iMG for Maintenance Planning Plant:
After the Logistics Plant is created then if it has the behavior of a Planning Plant then use the IMG below to create the Logistics Plant as a Planning Plant.


Below: the PLANT on the left (1st column) is the Maintenance Plant 1100 and 1200, and on the right (3rd column) is the Planning Plant 1100. In this case Planning is centrally done using Plant 1100 for the 2 Maintenance Plants.


Note case 1 of Planning Plant usage:
the Planning Plant is required when creating the Maintenance Order, it can be entered manually or defaulted from the Technical Object EQ of FL.


Note case 2 of Planning Plant usage:
when creating Task List (General Task List, Equipment Task List or Functional Location Task List), the Planning Plant is MANDATORY.


Monday, August 3, 2020

Question no 3716 : Maintenance Plant

In SAP PM as at ECC6.0 EhP6, which of the following are the use of Maintenance Plant ?

(more than one answers)

A)  Work Center creation.
B)  Maintenance Plane header.
C)  General Task List header.
D)  Location of Technical Object.
E)  Permit header.
.

click "1 comment" for suggested solution

Wednesday, December 11, 2019

Question no 3673 : Planning Plant

In SAP PM as at ECC6.0 EhP7, which of the following is where Planning Plant applicable ?

(more than one answers)

A)  General Task List Header as a mandatory field.
B)  Maintenance Plan Header as a mandatory field.
C)  Maintenance Order initial screen as a mandatory field.
D)  Maintenance Notification initial screen as a mandatory field.
E)  Work Center initial screen as a mandatory field.
.

Answers: A, C

B, D) Both Maintenance Plan and Maintenance Notification Header do not necessarilly require a Plant defination in its Header of Maintenance Item for certain Maintenance Plan acenario.
E) Work Center is created with maintenance Plant.
.

Monday, July 30, 2018

Question no 3572 : Planning Plant in Plant Maintanenace

In SAP PM as at ECC6.0 EhP6, which of the following are created with a Planning Plant ?

(more than one answers)

A)  Maintenance Work Center.
B)  Maintenance Task List.
C)  Maintenance Notification.
D)  Maintenance Order.
E)  Equipment Master.
.

Answer: B, D

A) Work Center is created with a Maintenance Plant.
C) Maintenance Notification does not work with a Plant.
D) Equipment Master need not be assigned to a Plant.

Wednesday, August 31, 2016

Question no 3243 : Maintenance Plant

In SAP PM as at ECC6.0 EhP6, which of the following can be assigned to Maintenance Plant ?

(more than one answers)

A)   Planner Group.
B)   Maintenance Work Center.
C)   Technical Object.
D)   Permits.
E)   Measuring Point.

Thursday, March 5, 2015

Question no 2665 : Plant Maintenance basic Enterprise assignments

In SAP PM (ECC6 EhP7), evaluate and choose the Correct Statements ?

(more than one answers)

A)   A maintenance plant can also be a maintenance planning plant.
B)   One of more maintenance planning plant can be assigned to a maintenance plant.
C)   One of more maintenance plant can be assigned to a maintenance planning plant.
D)   Each Order Type can be assigned to one of more maintenance plant.
E)   Each Order Type can be assigned to one of more maintenance planning plant.
.

Saturday, April 28, 2012

Question no 1556 : Planning Plant

In SAP PM, which of the following are correct about the Planning Plant ?

(more then one answers)

A)    Only one planning plant can be assigned to each maintenance plant in the customizing.
B)    A planning plant can be assigned with more then one planner groups in the customizing.
C)    The Planning plant must always be manually entered when creating the technical object.
D)    A General Task List can contain different Planning plants for each counter of the same Task List group.
E)    Planning plant is mandatory when creating a maintenance order.
.

Monday, December 19, 2011

Question no 1453 : Planning Plant

In SAP PM, which of the following statements are TRUE about the Planning Plant ?

(more then one answers)

A)     When a Logistics Plant is created, it is already a Planning Plant.
B)     Planner Groups are unique to Planning Plants in the Customizing.
C)     The Planning Plant entry is required in the initial screen of the Maintenance Order creation screen.
D)     The Planning Plant entry is required in the initial screen of the Notification creation screen.
E)     Assigning a Planning Plant in the Equipment Master is optional.
.

Thursday, March 10, 2011

Question no 1004 : PM Organization

In SAP PM, which of the following organization concepts are correct ?

(more then one answers)

A)     A logistics plant when created, it is also behave as a maintenance plant.
B)     Multiple maintenance planning plants can be assigned to a maintenance plant.
C)     A maintenance plant can be used as an organization for spare parts storage.
D)     Multiple planner groups can be assigned to a maintenance planning plant.
E)     A maintenance plant can only have one maintenance work center.
.

Wednesday, March 9, 2011

Question no 1003 : Purpose of Maintenance Plant

In SAP PM, the purpose of a Maintenance Plant can play which of the following role in a plant maintenance environment ?
(more then one answers)

A)     Location of Technical Object.
B)     Maintenance Work Center.
C)     Storage for spare parts.
D)     Assignment of Functional Locations.
E)     Assignment of Permits.
.

Tuesday, October 12, 2010

Question no : 564 PM Master Data Maintenance Plant Assignment

PLM300 Plant Maintenance
Unit 03 Technical Objects

Which of the following organizational elements are defaulted when the maintenance plant is allocated to a technical object such as an Equipment ?
(more then one answers)

A)    Company Code.
B)    Planning Plant.
C)    Cost Center.
D)    Maintenance Work Center.
E)    Controlling Area.
.

Question no : 563 PM Organization Concepts

PLM300 Plant Maintenance
Unit 02 Plant Maintenance Organization

Which of the following statements are NOT TRUE ?
(More then one answer)

A)  A planning plant can be assigned to more then one maintenance plant.
B)  One of the purpose of maintenance plant is to define the location of a technical object.
C)  A maintenance plant cannot be a planning plant at the same time.
D)  A planning plant need not be assigned to a company code.
E)   Planner Groups are to be created against both the planning plant and maintenance plant for the functions of planning and execution to be realized.

Sunday, October 10, 2010

Question no : 559 PM Organization Concepts

PLM300 Plant Maintenance
Unit 02 Plant Maintenance Organization

For a Manufacturing facility, it implements the Plant Maintenance Plant-specific planning scenario where only a single plant is used where all planning and maintenance activities are in one plant, ……
(more than one answers)

(A) The Maintenance Plant is also the Maintenance Planning Plant.

(B) Maintenance requirements may be planned in the same plant where it occurs; therefore, the Maintenance Plant = Maintenance Planning Plant = Logistics Plant.

(C) The Maintenance workshops and spare parts storage could either be at the same plant where the maintenance and planning occurs OR at another plant.

(D) Multiple Maintenance Plants are assigned to a Maintenance Planning Plant.

(E) The Procurement and Storage of spare parts could be at the same plant where the maintenance activity and maintenance planning is occurring.
.

Saturday, October 9, 2010

Question no : 558 PM Organization Concepts

PLM300 Plant Maintenance
Unit 02 Plant Maintenance Organization

Which of the following organization structuring setup are correct ?
(more than one answers)

(A) A Maintenance Plant can also be a Maintenance Planning Plant.

(B) When a Logistics Plant is first generated, it is also automatically generated as a Maintenance Plant.

(C) If Maintenance and Planning are carried out in same the Logistics Plant all the time; the Logistics Plant is also the Maintenance Plant as well as the Maintenance Planning Plant.

(D) Maintenance Work Centers are assigned to the Maintenance Plant or the Maintenance Planning Plant depending on the Plant Maintenance Scenario.

(E) Maintenance Planner Groups are assigned to the Maintenance Planning Plant.
.

Sunday, February 28, 2010

Question no : 305 PM Organization options

TERP10 (Unit 9) Plant Maintenance & Customer Service

In a Plant specific planning scenario:

(Select ONE best answer)

A)   The maintenance plant is the planning plant.
B)   Multiple maintenance plants are assigned to a planning plant.
C)   Multiple planning plants are assigned to a maintenance plant.
D)   No planning plant is necessary. 
E)   The logistics plant is not necessary. 

Saturday, February 27, 2010

Question no : 304 PM Organization Maintenance Planner

TERP10 (Unit 9) Plant Maintenance & Customer Service

The maintenance planner group is assigned to which organizational object ?

(Select ONE best answer)

A)   Maintenance Work Center.
B)   Maintenance Planning Plant.
C)   Maintenance Plant.
D)   Maintenance Planner.
E)   Maintenance Technical Object.
.