Question no : 791 PM Preventive Scheduling

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

In scheduling the maintenance plan, the maintenance orders scheduled can be:
(more than one answers)

(A) Re-started.
(B) Skipped.
(C) Confirmed.
(D) Fixed.
(E) Called.
.