Unit 04 Scheduling
For each order type, you can define the standard scheduling type. However, this can be changed on the header data screen for the service order. Each scheduling type refers to a scheduling method as below:
(only one answer)
I forward scheduling
II backward scheduling
III current date scheduling
IV no scheduling
(A) I, II, IV
(B) I, II, III
(C) I, II
(D) I, III, IV
(E) I, II, III, IV
.
Answer: E