Question no : 867 PM Execution Scheduling types

PLM315 Maintenance Processing: Operational Functions
Unit 04 Scheduling

For each order type, you can define the standard scheduling type. However, this can be changed on the header data screen for the service order. Each scheduling type refers to a scheduling method as below:
(only one answer)

I    forward scheduling
II   backward scheduling
III  current date scheduling
IV  no scheduling

(A) I, II, IV
(B) I, II, III
(C) I, II
(D) I, III, IV
(E) I, II, III, IV
.