Question no : 863 PM Execution Capacity Calculation

PLM315 Maintenance Processing: Operational Functions
Unit 03 Planning

This Question is based on data from Question no : 862
What is the total available capacity for a 5 days working week if one of four capacity units is not available for that week ?
(only one answer)

(A) 27 hours
(B) 90 hours
(C) 108 hours
(D) 81 hours
(E) 135 hours
.