Question no : 754 PM Preventive Relationships in Task List

PLM310 Preventive Maintenance
Unit 02 Management of Task Lists.

“The end of one operation is linked to the start of the following operation.” This type of relationship is represented by an _________ relationship.
(only one answer)

(A) The relationship is not possible.
(B) FF
(C) SF
(D) SS
(E) FS
.