Question no 4045 : Valid Receivers for Production Order Settlement

In SAP Cost Object Controlling for Production Orders, which of the following determination factors for "Valid Receivers" for Production Order Settlement ?

(more than one answers)

A. Costing Variant.
B. Valuation Variant.
C. Production Order Type.
D. Planning Plant.
E. Settlement Profile.

Answer: C, E

The Order Type (Plant independent) is assigned with a Settlement Profile and the configuration of the Settlement Profile determines the Valid Receivers.

Wednesday, December 2, 2020

Question no 3769 : Cost Collector in PP

In PP as at ECC6.0 EhP6, which of the following can use a Cost Collector to collect costs ?

(more than one answers)

A)  Repetitive Planned Orders.
B)  Planned Orders for Shop Floor Production.
C)  Production Orders.
D)  Planned Independent Requirement.
E)  Planning Scenario.
.

Click "1 comment" for possible solution.

Monday, July 11, 2016

Question no 3209 : Costing with Quantity Structure

In SAP PP or PPPI as at ECC6.0 EhP7, the Costing with Quantity Structure uses which of the following for Planned Cost Calculation ?

(more than one answers)

A)   BOM and Standard Routing.
B)   Recipe.
C)   Based Planning Object.
D)   Inspection Plan
E)   BOM and Rate Routing
.

Monday, April 28, 2014

Question no 2361 : Controlling BOM costing

In SAP CO-PCP, which of the following will have an impact of Costing Calculation for Material Cost-Estimate with Quantity Structure (BOM) ?

(more then one answers)

A)    The BOM Header Status.
B)    Item Category.
C)    Costing Relevancy.
D)    Fixed Quantity indicator.
E)    Scrap Factor.
.

Tuesday, November 5, 2013

Question no 2086 : Scrap Factor

In SAP CO-PCP, you can include the scrap factor in which of the following master data ?

(more then one answers)

A)    at Material Master MRP4 view, component scrap factor.
B)    at BOM item, component scrap factor.
C)    at Routing Operation detail, operation scrap factor.
D)    at BOM item, operation scrap factor.
E)    at Material Master MRP1 view, assembly scrap factor.
.

Sunday, November 3, 2013

Question no 2085 : Net Indicator for BOM Costing

In SAP CO-PCP ECC6.0, what is the purpose of the Net Indicator in the BOM item ?

(only one answer)

A)   Includes in the cost estimate the operation scrap for each BOM item and not the assembly scrap in the material master record.
B)   Includes in the cost estimate the assembly scarp factor for each BOM item and not the assembly scrap in the material master record.
C)   Includes in the cost estimate the  assembly scarp factor for each BOM item and not the operation scrap in the material master record.
D)   Includes in the cost estimate the operation scrap for each BOM item and not the operation scrap in the material master record.
E)   Includes in the cost estimate the operation scrap for each BOM item and not the operation scrap in the Routing operation.
.

Friday, November 1, 2013

Question no 2083 : BOM item costing control

In SAP CO-PCP, the method to control costing of a material in a Bills of Material is to use which of the following ?

(only one answer)

A)     Item Category.
B)     BOM Usage.
C)     BOM status.
D)     Item status.
E)     Costing Relevancy Indicator.
.

Question no 2082 : Settlement Rule

In SAP PM/PP/CO, the Settlement Rule assigned to the Maintenance Order is carried out due to which of the following parameter ?

(only one answer)

A)     Settlement Profile assigned to the Costing Variant.
B)     Settlement Rule assigned to the Costing Variant.
C)     Settlement Profile assigned to the Valuation Variant.
D)     Settlement Profile assigned to the Order type Plant-dependent Parameter.
E)     Settlement Profile assigned to the Order type Plant-independent Parameter. 
.


Tuesday, October 29, 2013

Question no 2079 : Costing Sheet

In SAP CO, the Costing Sheet is directly assigned to which of the following ?

(only one answer)

A)    Order type Plant independent parameter.
B)    Order type Plant dependent parameter.
C)    Costing Variant.
D)    Valuation Variant.
E)    Controlling Area.
.

Monday, October 28, 2013

Question no 2078 : Costing Sheet

In SAP CO, the costing sheet determines which of the following ?

(more then one answers)

A)   The Direct cost to which the overhead is applied to.
B)   The Overhead by percentage based, quantity based, or fixed amount.
C)   What Object is credited under what cost elements.
D)   Dependencies or conditions the overhead is applied.
E)   Which item category and Control Key subjected to Overhead Calculation.
.

Sunday, August 4, 2013

Question no 1994 : Qty Structure Costing

In SAP MM, PP, CO at ECC6.0, which of the following Data Key controls the method of Product Cost Estimate without Qty Structure for a particular Material ?

(only one answer)

A)    Costing Variant.
B)    Valuation Variant.
C)    Material Group.
D)    Valuation Category.
E)    Material Type.
.

Wednesday, September 12, 2012

Question no 1667: Controlling Product Cost Estimate

In SAP PP/CO ECC6.0, in order to control a material for product cost estimate calculation, especially for new product development until mass production, which of the following is your recommendation ?

(only one answer)

A)     Use the correct material type.
B)     Do not create the Bills of Material and Routing until mass production begins.
C)     Do not create the Costing view of the material master until mass production begins.
D)     Assign an appropriate material status to the material master.
E)     Set the item status in the BOM to control the "costing relevancy".
.

Thursday, September 29, 2011

Question no 1378 : Costing Variant

In SAP CO, the Costing Variant allows you to do the following ?

(more then one answers)

A)    Calculate the surcharge or overhead for internal orders.
B)    Calculate the surcharge or overhead for sales orders.
C)    Calculate the surcharge or overhead for production orders.
D)    Calculate the surcharge or overhead for purchase orders.
E)    Calculate the surcharge or overhead for maintenance orders.
.

Sunday, August 29, 2010

Question no : 466 CO Controlling Basic Concepts

TERP10 Quiz Unit 13 Management Accounting

A company wishes to track costs, and in some cases revenues for its events, within a controlling area. Which of the following Controlling areas would you recommend ? 

A)      Activity Based Costing.
B)      Product Cost Controlling.
C)      Product Cost Planning.
D)      Profitability Analysis.
E)      Internal Orders.
.

Question no : 465 CO Controlling Basic Concepts

TERP10 Quiz Unit 13 Management Accounting

_______________ deals mainly with analyzing the effects of enterprise activities on the external market forces. It also enables you to determine how successful the enterprise is in different market segments.

A)      Cost Element Accounting.
B)      Overhead Cost Controlling.
C)      Product Cost Accounting.
D)      Profitability Analysis.
E)      Profit Center Accounting.
.

Question no : 464 CO Controlling Basic Concepts

TERP10 Quiz Unit 13 Management Accounting

_______________ examines the origin of costs in the functional areas of an enterprise. 

A)      Cost Element Accounting.
B)      Overhead Cost Controlling.
C)      Product Cost Accounting.
D)      Profitability Analysis.
E)      Profit Center Accounting.
.

Question no : 463 CO Controlling Basic Concepts

TERP10 Quiz Unit 13 Management Accounting

Which of the highest level of Organizational unit in CO or Controlling or Management Accounting in SAP ? 

A)      Profit Center.
B)      Controlling Area. 
C)      Operating Concern.
D)      Group of Company. 
E)      Company.
.

Thursday, June 10, 2010

Question no : 357 CO Basic Concept

TERP10 Unit 13 Management Accounting 

A customer in the musical rental business wish to collect costs conducted in trade fairs, as well as to track costs for maintenance and repair work. Which of the following CO tool would be most appropriate ? 

(Select ONE best answer)

A)   Profit Center Accounting.
B)   Internal Orders.
C)   Cost Center Accounting. 
D)   Profitability Analysis. 
E)    Cost Object Controlling. 

Sunday, June 6, 2010

Question no : 356 CO Product Costing

TERP10 Unit 13 Management Accounting 

The costing sheet in Product Cost Planning and Cost Object Controlling allows you to: 

(Select ONE best answer)

A)   Calculate the Direct and Indirect Labor costs of a product or production. 
B)   Calculate the Activity costs of a product or production. 
C)   Calculate the Cost estimate of a product or production. 
D)   Calculate the Overhead cost of a product or production. 
E)    A basis for the formulation of Activity-Based-Costing of a product or production.