Question no 3854 : Process Quality Inspection for PP

In SAP PP/QM as at ECC6. 0 EhP6, which of the following settings are expected for initiating Process Quality Inspection for Production Order ?
(As at S/4 Hana 1909, same setup)

(more than one answers)

A)  Assign Inspection Point to the Routing Header.
B)  Assign Inspection Point to the Inspection Plan Header.
C)  Assign an appropriate Inspection Type to the Material Master.
D)  Activate a PP Order Type for QM.
E)  Assign Master Inspection Characteristics to he Routing Operation.
.

Answers: A, C, E

A, B) PQC uses the Routing Instead of the Inspection Plan, Inspection Point is therefore assign at the Routing.
C) Inspection Type 03
D) No specific requirement in activating QM in the PP Order Type.
E) Since it is Routing for PQC (Process Quality Control), therefore MICs are assigned to the Routing Operations.
The following are basic setup requirements:
1) Material Master QM data view assign Inspection Type 03.
2) Assign appropriate Inspection Point (eg: 150) in the Routing Header.
3) Assign appropriate Control Key (eg: PP06) to Routing Operation.
4) Assign QM Characteristics to Routing Operation with correct Sampling Procedure.
5) Set "Time" or "Quantity" related data in the Routing Operation detail.


Monday, January 4, 2021

Question no 3782 : Inspection Characteristics in Routing

In QM as at ECC6.0 EhP6, Inspection Characteristics assigned to the Routing is for which Inspection Type purpose ?

(only one answer)

A)  Inspection Type "01".
B)  Inspection Type "02".
C)  Inspection Type "03".
D)  Inspection Type "04".
E)  Inspection Type "05".
.

click "1 comment" to view Possible Solution

Monday, September 7, 2020

Question no 3731 : Process Quantiy Control

In SAP PP as at ECC6.0 EhP6, which of the following are the general setup required for PQC (Process Quality Control) for PP Production Order ?

(more than one answers)

A)  Assignment of Inspection Point in the Routing Header.
B)  Assignment of Inspection Point in the Header of the BOM.
C)  Assignment of Master Inspection Characteristics in the Routing Operation.
D)  Assignment of Master Inspection Characteristics in the BOM item.
E)  Assignment of an appropriate Inspection Type in the Material Master QM data view.
.

Answers: A, C, E

Thursday, June 11, 2015

Question no 3039 : Inspection Type 0130

In SAP ERP  Quality Management as at ECC6.0, which of the following are true  when implementing Inspection Type '0130' inspection for external operation for production orders?

(more than one answers)

A)  Assignment of MIC to Routing operation is required.
B)  Use of Inspection Plan with appropriate Usage for the inspection type is possible.
C)  Assignment and activation of inspection type 0130 to material QM view.
D)  Assignment of inspection type to Routing operation with external operation control key is a must.
E)  Inspection lot is created when Production Order is released.
.

Tuesday, March 10, 2015

Question no 2745 : Early Inspection before Production Order Goods Receipt

In SAP QM ECC6.0 EhP6, which inspection origin supports creation of inspection lot before production order goods receipt, the inspection lot is created when the production order is released ? This is so that Inspection can be done for the completed production goods before the stocks are posted to the warehouse stock in a goods receipt. 

(only one answer)

A) Inspection Origin 01.
B) Inspection Origin 02.
C) Inspection Origin 03. 
D) Inspection Origin 04.
E) Inspection Origin 05. 
.

Wednesday, August 13, 2014

Question no 2630 : Assignment of inspection type 0130

In SAP QM, where is the inspection type 0130 should be assigned to ensure the externl operation for a Routing Operatio  is subjected to Inspection Processing ?

(only one answer)

A)   Assign the Inspection Type at the Inspection Plan Header.
B)   Routing Header should be assigned with the Inspection Type.
C)   Assignment of the Inspection Type to the Control Key of the Operation in the Customizing.
D)   Production Order's Order type Plant-dependent parameter should be assinged with the Inspection Type.
E)   Assignment of the Inspection type to external operation detail in the Routing.
.

Question no 2628 : QM for External Processing in PP

In SAP QM for PP, which of the following Inspection type is suitable for Control Key PP02 where the External Process Purchase Order when Goods Receipt will generate an Inspection Lot for inspecting the works done by the external vendor for the Production Operation ?

(only one answer)

A)    Inspection type 01
B)    Inspection type 0130
C)    Inspection type 02
D)    Inspection type 03
E)    Inspection type 0310
.

Tuesday, July 15, 2014

Question no 2453 : Early Inspection Lot for Production Order

In SAP QM ECC6.0, which of the following are relevant settings for early creation of Inspection Lot so that Inspection can be executed before the goods receipt of the the production order ?

(more than one answers)

A)    "Control of inspection lot creation" indicator in the Quality Info Record.
B)    "Control of inspection lot creation" indicator in the Material Master QM view.
C)    Inspection Type "04" activated at the Material Master QM view.
D)    Inspection Type "03" activated at the Material Master QM view.
E)    "Control of inspection lot creation" indicator in the Order Type Plant dependent parameter.
.

Thursday, April 17, 2014

Question no 2350 : Early Inspection for Production Order

In SAP ECC6.0 QM, what parameter is to be setup to facilitate the Early Inspection at Goods Receipt for Production Orders ?

(only one answer)

A)    Inspection Type in the Configuration.
B)    Inspection Origin in the Configuration.
C)    Production Inspector Profile assigned to the QM view in the Material Master.
D)    Control Indicator in the Inspection Type assign at the QM view in the Material Master.
E)    Control Indicator in the QM Control Key assign at the QM view in the Material Master.
.