Question no : 800 PM Preventive Plan Start Date Calculation

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

Estimated annual performance = 73,000 liters
Total number of days in a year = 365 days

For the data in the above question, assume that the initial counter reading is 10,000 liters and Cycle due at 60,000 liters; what is the expected planned start date ?
(only one answer)

(A) in 50 days.
(B) in 100 days.
(C) in 150 days.
(D) in 200 days.
(E) in 250 days.
.

2 comments:

  1. 73,000 / 365 = 200 liters per day
    60,000 - 10,000 = 50,000 liters to due
    50,000 liters / 200 = 250 days to the due data