Question no : 478 PS Logistics Concepts

TERP10 (Unit 10) Program and Project Management 
.
An _____________ activity determines the output to be provided by machines or personnel in order to complete the activity. 
   
(Select ONE best answer)

A)   Cost activities.
B)   External services.
C)   Internal processing.
D)   External processing. 
E)    3rd party order.
. 

Sunday, August 29, 2010

Question no : 450 PS Logistics Concepts

TERP10 Quiz Unit 10 Program and Project Management

The phases in a Project includes the following EXCEPT ? 

A)      Rough-Cut Planning.
B)      Detailed Planning.
C)      Execution.
D)      Period End Closing.
E)      Collaboration.
.

Saturday, February 20, 2010

Question no : 296 PS Logistics Cycle Analysis


TERP10 (Unit 10) Project System 

Cycle analysis is to analyze any in-consistencies in a closed sequence of relationship and activities which can only be done in:

(Select ONE best answer)

A)   Network graphics.
B)   Periodic processing. 
C)   Milestone.
D)   Work breakdown structure.