Unit 05 Maintenance Planning with Strategy: Performance-Based
If the duration of the cycle is 250 days and the call horizon is either 0%, 80%, or 100% respectively; what are the call dates that the system creates for each call horizon scenario, the call date below is # days from the 1st day in the cycle duration ?
(only one answer)
(A) 0 day, 200 days, 250 days from the 1st day for each order respectively.
(B) 250 days, 250 days, 250 days from the 1st day for each order respectively.
(C) 0 day, 0 day, 0 day from the 1st day for each order respectively.
(D) 200 days, 200 days, 250 days from the 1st day for each order respectively.
(E) 0 days, 0 days, 250 days from the 1st day for each order respectively.
.
Answer: A