Question no : 795 PM Preventive Initialization of Measuring Point

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

The initial measurement document is the first measurement document that is entered for a newly added counter; the purpose of this initial entry is:
(only one answer)

_____ (A) It is automatically determined from the estimated annual performance entry in the counter; therefore manual entry is not required.
_____ (B) It is necessary as the maintenance plan cannot be started without an initial reading recording.
_____ (C) It represents the current counter reading at the time of the measurement counter.
_____ (D) It is not necessary as the maintenance plan is started with the estimated annual performance figure.
_____ (E) It provides the planned costs for the first maintenance order called.
.