Question no : 810 PM Preventive Condition Based

PLM310 Preventive Maintenance
Unit 08 Condition-Based Maintenance

If the compressor at your company breaks down, the repair is automatically triggered by the transmission of the current condition data. For example, if a motor in the compressor breaks down, a specific malfunction code is transmitted, which triggers a corresponding notification in the PM component of the R/3 System. Which preventive maintenance scenario is applicable ?
(only one answer)

(A) Time-Based Maintenance Planning Strategy.
(B) Performance-Based Maintenance Planning Strategy.
(C) Condition-Based Maintenance Planning.
(D) Sales-of-Service-Based Maintenance Planning.
(E) Single-Cycle Maintenance Planning.
.