Question no : 874 PM Execution Process Permits

PLM315 Maintenance Processing: Operational Functions
Unit 04 Scheduling

In setting up for process-oriented permits, you proceed with the following sequence:
(only one answer)

I    Characteristics are created in the classification system with reference to fields in the order header.
II   Assign the characteristics to a class of class type 049 (permits).
III  The permit class must be assigned to a permit group.
IV  Assign the permit class to the order type.
V   A permit is created and classified.

(A) I, III, IV, V
(B) I, II, IV, V
(C) I, II, IV, V
(D) I, II, III, V 
(E) I, II, III, IV, V
.