Question no : 777 PM Preventive Date Calculations

PLM310 Preventive Maintenance
Unit 03 Maintenance Planning with Single Cycle

Use the data in Question 9 for this question; assuming the Call Horizon is 50%, what is the Call date and Planned date for the 2nd order ?
(only one answer)

(A) Call date is 15.05.2004 and Planned date is 01.07.2004
(B) Call date is 01.04.2004 and Planned date is 01.07.2004
(C) Call date is 01.06.2004 and Planned date is 01.07.2004
(D) Call date is 01.07.2004 and Planned date is 01.07.2004
(E) Call date is 01.01.2004 and Planned date is 01.07.2004
.