Unit 03 Maintenance Planning with Single Cycle
Determine the various dates from the following scheduling parameters if we perform a maintenance schedule today (refer to “Today date” below):
(more than one answers)
Strategy type: Time-Based
Cycle: 3 months
Scheduling period 1 year
Scheduling indicator: Time (calendar)
Cycle start date 01.01.2004
Today date 01.12.2003
(A) If the Call Horizon = 0%, the Call date for the 2nd order is 01.04.2004 and the Planned date is 01.07.2004
(B) If the Call Horizon = 0%, the Call date for the 2nd order is 01.12.2003 and the Planned date is 01.07.2004
(C) If the Call Horizon = 100%, the Call date for the 2nd order is 01.04.2004 and the Planned date is 01.07.2004
(D) If the Call Horizon = 100%, the Call date for the 2nd order is 01.07.2004 and the Planned date is 01.07.2004
(E) If the Call Horizon = 100%, the Call date for the 2nd order is 01.12.2004 and the Planned date is 01.07.2004
.
Answer: A, D