Question no : 788 PM Preventive Maintenance Package

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

Which data element you have to set to ensure a package is executed only once from the maintenance package ?
(only one answer)

(A) SF later confirmation = 100%.
(B) Call Horizon.
(C) Offset.
(D) SF later confirmation = 0%.
(E) Tolerance (+) for SF = 0%.
.