Question no : 785 PM Preventive External Service Plan

PLM310 Preventive Maintenance
Unit 03 Maintenance Planning with Single Cycle

For the “maintenance-plan-based service” procurement scenario, the purpose of the service specification is to:
(only one answer)

(A) collect the service masters to be called into service entry sheets when the maintenance plan is scheduled.
(B) specify the service tasks to be copied to the settlement order when the maintenance plan is schedule.
(C) indicate the framework purchase order number as well as the service masters to be called into service entry sheets when the maintenance plan is scheduled.
(D) include service tasks, framework purchase order, and service masters to be called into service entry sheets when the maintenance plan is scheduled.
(E) specify service documents from the DMS (Document Management System) to be copied to the settlement order when the maintenance plan is scheduled.
.