Question no : 750 PM Preventive Control Key in Task List

PLM310 Preventive Maintenance
Unit 02 Management of Task Lists.

Operational control key provides the following control parameter:
(more than one answers)

(A) included in scheduling.
(B) confirmation requirement.
(C) relevancy to costing.
(D) internal or external operations.
(E) print control.
.