This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, December 2, 2010

Question no : 786 PM Preventive Hierarchy in Maintenance Package

PLM310 Preventive Maintenance
Unit 04 Maintenance Planning with Strategy: Time-Based

The hierarchy of maintenance packages defines how maintenance packages are to be executed:
(more than one answers)

(A) If maintenance packages have different hierarchy levels, the maintenance package with the higher level will determine which operations will be included in the called object.

(A) If maintenance packages have different hierarchy levels, the maintenance package with the lower level will determine which operations will be included in the called object.

(C) If maintenance packages have different hierarchy levels, the maintenance package with the lower level always ignored.

(D) If maintenance packages with the same hierarchy level coincide, these maintenance packages are executed together.

(E) If maintenance packages have different hierarchy levels, the maintenance package with the lower level may include the operations depending on the setup in the maintenance package rules.
.

1 comment: