Question no : 773 PM Preventive Date Calculation

PLM310 Preventive Maintenance
Unit 03 Maintenance Planning with Single Cycle

In order to set the planned date equals the call date, you have to:
(only one answer)

(A) set the “Call Horizon” in the maintenance plan scheduling parameter to 0%.
(B) set the “Call Horizon” in the maintenance plan scheduling parameter to 100%.
(C) set the “Scheduling period” in the maintenance plan scheduling parameter to equal the Plan cycle time.
(D) set the “Scheduling period” in the maintenance plan scheduling parameter to 1 year.
(E) Set the “equal to planned date” selection indicator when calling an order.
.