This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, November 25, 2010

Question no : 679 PM WCM Concepts

PLM300 Plant Maintenance
Unit 09 Work Clearance Management

Which of the process step must be completed before the maintenance order managed with WCM can be technically completed ?
(only one answer)

(A) Un-tagging performed at Work Clearance Document.
(B) Un-tagging performed at Work Clearance Application.
(C) Un-tagging performed at Work Approval.
(D) Un-tagging performed at Work Clearance Document and Work Clearance Application.
(E) Un-tagging performed at Work Clearance Application and Work Approval.
.

1 comment: