Question no : 657 PM Preventive Strategy Concept

PLM300 Plant Maintenance
Unit 07 Preventive Maintenance

Which of the following statements are True ?
(more than one answers)

(A) Time-based Preventive Maintenance plans are triggered after a specific period of time has elapsed.
(B) Maintenance Task Lists can be used to standardize recurring activities.
(C) The packages for a strategy can have difference cycle units, such as month, year, but they must always have the same dimension, such as time.
(D) Maintenance item consists of planning data, reference objects, and task lists.
(E) Planned dates define the date from which the calculation of the cycle date begins.
.