This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, November 25, 2010

Question no : 676 PM Project Based PM

PLM300 Plant Maintenance
Unit 08 Project Oriented Maintenance

When management maintenance using project based maintenance:
(more than one answers)

(A) it is necessary to use maintenance notification.
(B) it is not necessary to use maintenance notification.
(C) it is possible not to use project dates for scheduling the maintenance order.
(D) it is mandatory to use project dates for scheduling the maintenance order.
(E) it is not necessary to settle the maintenance order against a WBS element.
.

1 comment:

Note: Only a member of this blog may post a comment.