Question no : 674 PM Project Based Maintenance

PLM300 Plant Maintenance
Unit 08 Project Oriented Maintenance

For Project based maintenance, components procured are to be received into which type of special stocks ?
(only one answer)

(A) WBS element.
(B) Project definition.
(C) Sales order.
(D) Maintenance order.
(E) Common stock .
.