Question no : 641 PM Refurbishment Concept

PLM300 Plant Maintenance
Unit 06 Refurbishment of Spare Parts

What are the stock value during processing of the refurbishment order of Actual condition C3 to Target condition C2 ?

Price control at the valuation area level is “V” with a MAP (Moving average price of 800). The total replacement costs is measured at $ 400.

Stock value before processing.            
Condition
Price
Quantity
Stock value
Price control
C1
1000
10
$ 10000
“S”
C2
2000
10
$ 20000
“S”
C3
500
20
$ 10000
“S”
$ 40000
Total value
 $ 800
Per unit

(more than one answers)

(A)  C3 with 19 units at stock value of $ 9500.
(B)  C3 with 19 units at stock value of $ 9200.
(C)  C2 with 11 units at stock value of $ 22000.
(D)  C2 with 11 units at stock value of $ 20800.
(E)   C2 with 11 units at stock value of $ 20400.
.

2 comments:

  1. Valuation area level of MAP $800 is only statistical and not used for stock valuation.
    The actual valuation is at the Valuation type of C1, C2, C3.
    In this Case:
    C3: (20-1) x $500 = $9500
    C2: (10+1) x $2000 = $2200

    ReplyDelete