PLM300 Plant Maintenance
Unit 07 Preventive Maintenance
Which of the following object assignments are correct ?
(more than one answers)
(A) only one maintenance item can be assigned to the maintenance plan.
(B) more than one maintenance items can be assigned to the maintenance plan.
(C) only one maintenance strategy can be assigned to the task list.
(D) more than one maintenance strategy can be assigned to the task list.
(E) every operations in the task list must have a maintenance package.
.
Answer: B, C