In SAP MM and PP, MRP can be set to automatically generate which of the following MRP elements ?

(more then one answers)

A)    Purchase Requisition.
B)    Purchase Order.
C)    Release Order against Contract.
D)    Delivery Schedule against Scheduling Agreement.
E)    Production Order.
,