This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Saturday, August 13, 2011

Question no 1341 : MRP run option


In SAP PP, when performing the MRP run option with "Lead Time Scheduling", what is he correct reaction of the MRP Program ?

(only one answer)

A)    If the Material does not have a Routing, the MRP program will be terminated immediately.

B)    If the Material does not have a Routing, the MRP program will check for the MRP 2 view's "In-house Production time" and if it is not setup, the MRP program will be terminated immediately.

C)    The MRP program will check for the MRP 2 view's "In-house Production time" and if it is not setup, it will then check if the material has a Routing and if no Routing is found,  the MRP program will be terminated immediately.

D)    The Routing is be looked at first, if not found; it will look for the Lot-Size dependent time data in the Work Scheduling view, and at last if not available; then it will check for the MRP 2 view's "In-house Production time"; if all were not setup then MRP program will be terminated immediately.

E)     The Routing is be looked at first, if not found; it will look for the Lot-Size dependent time data in the Work Scheduling view, and at last if not available; then it will check for the MRP 2 view's "In-house Production time"; if all were not setup then MRP program will continue calculation without the detail scheduling.
.

1 comment:

Note: Only a member of this blog may post a comment.