Question no 1339 : How to attach a drawing to a BOM

In SAP PP, what would you suggest to attach a drawing to a Bills of Material ?

(only one answer)

A)   use item category "L", assign a material with a document from DMS.
B)   assign a document from DMS to the BOM header.
C)   the header material of the BOM's material master if assigned with a document from DMS will automatically be copied to the BOM header.
D)   use item category "D", assign the document from DMS to the BOM as a BOM item.
E)   any BOM item can be assigned with a document from DMS as long as the BOM usage is configured with a Document folder.
.

1 comment:

  1. Item category D at the BOM item allows assignment of document from the DMS system.

    ReplyDelete