In SAP PP, when an assembly production order is to be automatically created when it's parent production order is created and no inventory management is required for the assembly item as the goods receipt of the assembly will directly be charged to parent production order. Which of the following production concept setup do you think will be appropriate ?
(only one answer)
A) Phantom assembly for the assembly as the BOM item.
B) Backflushing.
C) Collective orders.
D) Special procurement "Phantom assembly".
E) Individual/Collective Indicator "2".
.
Answer: C
ReplyDelete