Question no 1340 : MRP run option

In SAP PP Planning, which of the following is not a mandatory field in the MRP views ?

(only one answer)

A)     MRP type.
B)     MRP controller.
C)     Lot Size Key.
D)     Scheduling Margin Key.
E)     Safety Stock.
.

2 comments:

  1. If you select a valid MRP type which is relevant for MRP, the MRP Controller, Lot Sizing Key in the MRP 1 view is mandatory. In addition, the Scheduling Margin Key and Planned Delivery time (for external procuremnt) in the MRP 2 view would also be necessary. However, the safety stock is optional.

    ReplyDelete
  2. For MRP type with Auto Reorder Point with Safety Stock, then the safety stock is necessary. In conclusion, safety stock field is generally an optional field in most cases.

    ReplyDelete